Historical information
Use of outside vendors
Change control processes
Human resource skill level requirements
第1题:
Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A . Overhead rates, labor rates and material costs.
B . Overhead rates, schedule slippages, and rework.
C . Rework, cost-of-living adjustments, and overtime.
D . Material costs, shipping cost, and scope changes.
E . Labor rates, material costs, and cost reporting.
第2题:
By which means is a contractor able to control cost overruns due to changing requirements?
A Project data review
B Change order
C Purchase order amendment
D Change control
E None of the above.
第3题:
Sources for data on activity durations and resource requirements can be gathered from which of the following:
A.Past project records (historical data)
B.Commercial techniques (standard practices, rules of thumb)
C.Past project team members knowledge (experience, oldtimers)
D.All of the above
E.A and C only
第4题:
151 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A. Past project records (historical data)
B. Commercial techniques (standard practices, rules of thumb)
C. Past project team members knowledge (experience, oldtimers)
D. All of the above
E. A and C only
第5题:
19 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A. Direct labor dollars
B. Direct labor hours.
C. Overhead rates.
D. Procurement costs.
E. None of the above
第6题:
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)
A. work performance information
B. scope statement
C. change requests
D. process analysis
第7题:
144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A. Overhead rates, labor rates and material costs.
B. Overhead rates, schedule slippages, and rework.
C. Rework, cost-of-living adjustments, and overtime.
D. Material costs, shipping cost, and scope changes.
E. Labor rates, material costs, and cost reporting
第8题:
It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A . Direct labor dollars
B . Direct labor hours.
C . Overhead rates.
D . Procurement costs.
E . None of the above.
第9题:
139 By which means is a contractor able to control cost overruns due to changing requirements? A. Project data review
B. Change order
C. Purchase order amendment
D. Change control
E. None of the above
第10题:
● Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above
E A and C only