第1题:
By which means is a contractor able to control cost overruns due to changing requirements?
A Project data review
B Change order
C Purchase order amendment
D Change control
E None of the above.
第2题:
139 By which means is a contractor able to control cost overruns due to changing requirements? A. Project data review
B. Change order
C. Purchase order amendment
D. Change control
E. None of the above
第3题:
The purpose of configuration management is to:
A.insure drawings are updated
B.control change throughout the project
C.control change during the production only
D.generate engineering change proposals
E.inform. the project manager of changes
第4题:
● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.
(75)
A. proceedings
B. controls
C. forecasting’s
D. prelibations
第5题:
● The purpose of configuration management is to:
A insure drawings are updated
B control change throughout the project
C control change during the production only
D generate engineering change proposals
E inform. the project manager of changes
第6题:
The "buy or make" decision is usually made during the:
A acquisition cycle
B contract evaluation cycle
C requirements cycle
D pre-award cycle
E at any time that is convenient for the project manager
第7题:
33 The purpose of configuration management is to:
A. insure drawings are updated
B. control change throughout the project
C. control change during the production only
D. generate engineering change proposals
E. inform. the project manager of changes
第8题:
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)
A. work performance information
B. scope statement
C. change requests
D. process analysis
第9题:
● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:
· (73) all changes to the requirements
· Maintaining the relationships among the requirements, the project plansand the work products
· ……
(73)
A. Monitoring
B. Managing
C. Gathering
D. Reducin
第10题:
● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
(73)
A.executive IT manager
B.project manger
C.change control board
D.project sponsor