During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of

题目
During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of the project scope,()is the person with real approval power.

A.user
B.project manager
C.CCB
D.Project investor
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第2题:

● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A Change the scope baseline

B Prepare a variance report

C Call a meeting of the configuration control board

D Change the project's objectives

E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第3题:

In a matrix organizational form, MBO may be difficult to implement:

A . If the functional employees are supervised closely by the line manager rather than the project manager

B . Unless the project manager has an input into the employee's performance review

C . Unless the project and line managers agree on the ultimate objective

D . Unless the project and line managers agree to the duration of the task

E . None of the above are correct answers


正确答案:E

第4题:

● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

(73) A. change the scope baseline

B. contact the customer to determine if the change adds value

C. call a meeting of the change control board

D. change the project' s objectives


正确答案:B

第5题:

● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).

(75)

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:B

第6题:

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

A.Benefitcontribution

B.Expertjudgment

C.Scoringmodels

D.Flowcharting


参考答案:D

第7题:

● A clear definition of the user's needs serves as the direct basis for the:

A Work breakdown structure.

B Functional requirements.

C Project cost estimate.

D Selection of personnel.

E Termination decision.


正确答案:B

第8题:

174 In a matrix organizational form, MBO may be difficult to implement:

A. If the functional employees are supervised closely by the line manager rather than the project manager

B. Unless the project manager has an input into the employee's performance review C. Unless the project and line managers agree on the ultimate objective

D. Unless the project and line managers agree to the duration of the task

E. None of the above are correct answers


正确答案:E

第9题:

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.

(75)

A. proceedings

B. controls

C. forecasting’s

D. prelibations


正确答案:B

第10题:

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

A.executive IT manager

B.project manger

C.change control board

D.project sponsor


正确答案:C
试题(73)分析
 项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。
参考答案
(73)C