Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance. () is a method that analyze all

题目
Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance. () is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

A.Cost-Benefit
B.Control charts
C.Quality function deployment
D.Cost of quality analysis
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第2题:

● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

A.performance

B.process

C.product

D.object


正确答案:C

第3题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第4题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

第5题:

______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

A.euality assurance(QA)

B.Quality planning

C.Quality control(QC)

D.Quality costs


正确答案:A
解析:质量计划是质量管理的一部分,致力于制定质量目标,并规定必要的运行过程和相关资源以实现项目质量目标。
  质量控制就是项目团队的管理人员采取有效措施,监督项目的具体实施结果,判断它们是否符合项目有关的质量标准,并消除产生不良结果原因的途径。
  质量成本是指为满足质量要求所付出的主要成本。
  质量保证是通过对质量计划的系统实施,确保项目需要的相关过程达到预期要求的质量活动。选项A是质量保证(QA),选项B是质量计划,选项C是质量控制(QC),选项D是质量成本。因此应选择A。

第6题:

● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

(73)

A. Quality assurance (QA)

B. Quality planning

C. Quality control (QC)

D. Quality costs


正确答案:A

第7题:

The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

A.Manage quality

B.Quality audit

C.Quality metrics

D.Quality improvement


正确答案:A

第8题:

● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

(74)

A. quality planning

B. quality assurance

C. quality performance

D. quality control


正确答案:D

第9题:

Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control


正确答案:D
执行质量控制(quality control)指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

第10题:

● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs


正确答案:A
质量保证是一项有计划的、系统的质量活动,以确保项目的所有过程达到并符合要求。