第1题:
41 In the project environment, the individual ultimately responsible for quality control is:
A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D. The project manager who has ultimate responsibility for the entire project.
E.the customer who must ensure that he is receiving a quality product from the vendor
第2题:
● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.
A.performance
B.process
C.product
D.object
第3题:
In the project environment, the individual ultimately responsible for quality control is:
A . The line workers who must strive "to do things right the first time" to avoid quality problems.
B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D . The project manager who has ultimate responsibility for the entire project.
E . the customer who must ensure that he is receiving a quality product from the vendor.
第4题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第5题:
______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
A.euality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
第6题:
● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
(73)
A. Quality assurance (QA)
B. Quality planning
C. Quality control (QC)
D. Quality costs
第7题:
The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.
A.Manage quality
B.Quality audit
C.Quality metrics
D.Quality improvement
第8题:
● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
(74)
A. quality planning
B. quality assurance
C. quality performance
D. quality control
第9题:
Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control
第10题:
● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs