Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.

题目
Your have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. ( ) document provides this information.

A.Resource assignment matrix
B.Change control plan
C.Project charter
D.Client organization chart
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第2题:

● The use of the project reports:

A are not necessary on small projects

B provides a means whereby various levels of authority can judge project performance

C provides insight into project areas and the effectiveness of the control systems

D All of the above

E B and C


正确答案:E

第3题:

The use of the project reports:

A.are not necessary on small projects

B.provides a means whereby various levels of authority can judge project performance

C.provides insight into project areas and the effectiveness of the control systems

D.All of the above

E.B and C


正确答案:E
E

第4题:

Simile is applied in ________.

A、In politics, a reformer may have just as strong a love of power as a despot.

B、And is it not, perhaps, a drug which—like opium—has to be taken in continually stronger doses to produce the desired effect?

C、When the Arabs, who had been used to living sparing


参考答案:AB

第5题:

The(70)provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan

B.contract

C.project human resource plan

D.project charter


正确答案:D
解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

第6题:

182 The use of the project reports:

A. are not necessary on small projects

B. provides a means whereby various levels of authority can judge project performance

C. provides insight into project areas and the effectiveness of the control systems

D. All of the above

E. B and C


正确答案:E

第7题:

● The project life-cycle can be described as(72).

(72)

A.project concept, project planning, project execution, and project close-out

B.project planning, work authorization, and project reporting

C.project planning, project control, project definition, WBS development, and project termination

D.project concept, project execution, and project reporting


正确答案:A

试题(72)分析
  关于项目周期划分正确的是  (72)  。
  A.启动、计划、执行、收尾
  B.计划、授权、报告
  C.计划、控制、方案设计、WBS的发展、终止
  D.启动、执行、报告
参考答案
  (72)A

第8题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第9题:

The( )provides the project manager with the authority to apply organizational resources to project activities。

A.project management plan

B.project charter

C.project human resource plan

D.project stakeholders


正确答案:B
项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

第10题:

You develop a Web control. The Web control consists of labels and associated text boxes.You need to ensure that the Web control has both toolbox and visual designer support. What should you do?()

A. Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.

B. Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.

C. Add a Web User Control to your project. Define a class that inherits from UserControl.

D. Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.


参考答案:A