()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management
第1题:
Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
第2题:
108 Risk mitigation is the process of _____ .
A. transferring risk to another party.
B. reducing uncertainty on the project
C. identifying all possible risk events
D. monitoring status and making adjustments
E. All of the above
第3题:
● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
.Risk Monitoring and Control
第4题:
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).
(73)A. project management plan
B. project baseline
C. risk response plan
D. risk baseline
第5题:
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
第6题:
26 Risk mitigation is the process of _____ .
A. transferring risk to another party.
B. reducing uncertainty on the project
C. identifying all possible risk events
D. monitoring status and making adjustments
E. All of the above.
第7题:
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.
(71)
A. Quantitative Risk Analysis
B. Qualitative Risk Analysis
C. Enterprise Environmental Factors
D. Risk Management Plan
第8题:
Risk mitigation is the process of _____ .
A transferring risk to another party.
B reducing uncertainty on the project
C identifying all possible risk events
D monitoring status and making adjustments
E All of the above.
第9题:
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
第10题:
Workarounds are determined during which risk management process? (75).
A. Risk identification
B. Quantitative risk analysis
C. Plan risk responses
D. Risk monitoring and control