单选题Why is it important to have a final meeting on a project that has been cancelled?()A Document lessons learnedB Assign responsibilityC Close budgetD Begin new project

题目
单选题
Why is it important to have a final meeting on a project that has been cancelled?()
A

Document lessons learned

B

Assign responsibility

C

Close budget

D

Begin new project

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Of the following, who has the ultimate responsibility for meeting project quality objectives?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner


正确答案:B

第2题:

The following reports are normally developed during the project closure phase?

A Communications Management Plan and Lessons Learned

B Records Archive, Closure Report, lessons learned & Formal Acceptance Report

C Records Archive, Closure Report, & Specifications Document

D Communications Management Plan and Closure report

E None of the above


正确答案:B

第3题:

You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:

A.The project is operating at a favorable cost efficiency ratio.

B.the project is spending more than planned

C.the project is behind schedule

D.the project is ahead of schedule

E.B and C


正确答案:C
C

第4题:

● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).

(75)

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:B

第5题:

39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:

A. The project is operating at a favorable cost efficiency ratio.

B. the project is spending more than planned

C. the project is behind schedule

D. the project is ahead of schedule

E. B and C


正确答案:C

第6题:

Which of the following tools and techniques can be used to collect information for the project closure reports?

A Customer Surveys

B Brainstorming

C Document and Performance Analysis

D Lessons Learned

E All of the above


正确答案:E

第7题:

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner


正确答案:B

第8题:

During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

A . The project will be completed late.

B . The critical path has been lengthened.

C . the costs are being overrun.

D . Overtime will be required to maintain the original critical path.

E . None of the above.


正确答案:E

第9题:

97 The following reports are normally developed during the project closure phase?

A. Communications Management Plan and Lessons Learned

B. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

C. Records Archive, Closure Report, & Specifications Document

D. Communications Management Plan and Closure report

E. None of the above


正确答案:B

第10题:

A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:D
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
  选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
  由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。

更多相关问题