第1题:
Project Risk _____ .
A should not be calculated for small projects.
B is the probability of each risk event minus the sum of the consequences of potential risk events.
C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D cannot be quantified for first time projects.
E B or D
第2题:
Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
第3题:
The technique most commonly used to determine the profitability of a project includes _____ methods.
A . Net present value (NPV).
B . Return on investment (ROI).
C . Discounted cash flow (DCF)
D . Payout time and risk sensitivity analysis.
E . All of the above.
第4题:
Risk management allows the project manager and the project team to:
A eliminate most risks during the planning phase of the project
B identify project risks
C identify impacts of various risks
D plan suitable responses
E B, C and D only
第5题:
Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
第6题:
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
第7题:
The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A Is accomplished by paying the actual costs to the contractor.
B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C Is an undisclosed contingency in the contractor's bid.
D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E B and C
第8题:
"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .
A be completed in reduced overall time than other projects.
B be in a higher risk category than other projects.
C not be compatible with project risk and assessment
D A and B
E All of the above.
第9题:
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第10题:
111 It is useful to conduct project risk assessment according to the project's
A. charter
B. statement of work
C. Work Breakdown structure
D. network
E. budget