The most crucial time for project risk assessment is ( ) .

题目
The most crucial time for project risk assessment is ( ) .

A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Project Risk _____ .

A should not be calculated for small projects.

B is the probability of each risk event minus the sum of the consequences of potential risk events.

C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.

D cannot be quantified for first time projects.

E B or D


正确答案:C

第2题:

Amount at Stake is the _____ .

A function of planned time/real time project costs.

B risk identified in successful project completions.

C (Standard Project Deviation + Expected Costs)/6

D cost of investment loss + least cost to restore status quo.

E inherent risk at conception altered by standard project deviations.


正确答案:D

第3题:

The technique most commonly used to determine the profitability of a project includes _____ methods.

A . Net present value (NPV).

B . Return on investment (ROI).

C . Discounted cash flow (DCF)

D . Payout time and risk sensitivity analysis.

E . All of the above.


正确答案:E

第4题:

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only


正确答案:E

第5题:

Which of the following actions is an example of risk response:

A adjust project parameters (scope, time, quality ...)

B reduce the probability of potential project risk events

C reduce the consequences of potential project risk events

D wait until a problem actually happens, then deal with it in the most effective and efficient manner.

E A, B and C only


正确答案:E

第6题:

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.


正确答案:B

第7题:

The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .

A Is accomplished by paying the actual costs to the contractor.

B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).

C Is an undisclosed contingency in the contractor's bid.

D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.

E B and C


正确答案:C

第8题:

"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

A be completed in reduced overall time than other projects.

B be in a higher risk category than other projects.

C not be compatible with project risk and assessment

D A and B

E All of the above.


正确答案:D

第9题:

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget


正确答案:C

第10题:

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget


正确答案:C

更多相关问题