A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()A、Support for10Gb internal networkB、Support for SSDC、Support for integrated disk drivesD、Support for8Gb FC Switch Modules

题目

A customer is considering BladeCenter H and S chassis. Which of the following is a reason to implement BladeCenter H?()

  • A、Support for10Gb internal network
  • B、Support for SSD
  • C、Support for integrated disk drives
  • D、Support for8Gb FC Switch Modules
参考答案和解析
正确答案:A
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which three capabilities make the Cisco Nexus 7010 switch an effective solution for the data center core? ()

  • A、 virtualization
  • B、 unified I/O
  • C、 support for 48-port Gb/s line card
  • D、 support for Data Center Service Modules
  • E、 high performance
  • F、 high availability

正确答案:B,E,F

第2题:

A customer is involved in an IBM critical situation (CritSit). The customer recently installed iDATAPIex. The business partner has been assessed a significant penalty by IBM. Which of the following is the reason for this action by IBM?()

  • A、The business partner was required to perform a TDA and failed to do so
  • B、The business partner recommended a nonworking configuration
  • C、The business partner did not support the customer correctly
  • D、The business partner failed to sell Remote Technical Support (RTS)

正确答案:A

第3题:

A network administrator has installed an N7K-F248-25XP module into an existing chassis. The module is powered on, but the interfaces are all in VDC0. What is the reason for this?()   

  • A、 The chassis needs an EPLD upgrade to support the new module type.
  • B、 The default VDC cannot support F2 modules.
  • C、 The interfaces must be allocated into a VDC for F2 modules only.
  • D、 The module has failed GOLD diagnostics, and the switch has isolated the ports to protect the integrity of the system.

正确答案:C

第4题:

GSN是什么的缩写?()

  • A、GPRS Service Network
  • B、GPRS Service Node
  • C、GPRS support Node
  • D、GPRS support Network

正确答案:C

第5题:

A banking customer plans to implement a BladeCenter H chassis. They plan for seven HS22 blades, six HX5 blades with MAX5, one 1U external Fibre Channel switch, and two 3U Fibre Channel storage devices with fourteen 146GB drives. Which is the minimum amount of rack space required to implement the solution of the following?()

  • A、32U
  • B、21U
  • C、25U
  • D、22U

正确答案:C

第6题:

Which of the following services offers scheduled telephone support for complex questions on AIX systems?()

  • A、Techline
  • B、Consultline
  • C、Operational Support Services - Alert for pSeries
  • D、Operational Support Services - RS/6000 SystemWatch

正确答案:B

第7题:

CIOs and their staff have very little experience architecting or designing solutions to support unknown workloads. As executives focus on compliance issues, more systems must be architected to align with emerging or poorly defined requirements. If the customer prefers an integrated solution physically consolidated in a scalable, single framework that can connect to an enterprise class storage area network,  what solution would you recommend?()

  • A、Multiple 1U and 2U servers equipped with FC HBAs to connect to the enterprise SAN
  • B、Single 3U/4U servers expandable to 32-way equipped with FC HBAs to connect to the enterprise SAN
  • C、BladeCenter, expandable to 14 blades equipped with FC HBAs, and redundant 20-port FC SAN Switch modules to connect to enterprise SAN
  • D、IBM 1350 Cluster equipped with FC HBAs to connect to enterprise SAN

正确答案:C

第8题:

Which implement phase service component consists of explaining the benefits and limitations of purchased support options to a customer and ensuring that the customer understands operational processes and responsibilities? Select exactly 1 answer(s) from the following:()。

  • A、Staging and System Migration
  • B、Post Implementation Support Handoff Meeting
  • C、Detailed Design Development
  • D、Staff Training

正确答案:B

第9题:

A customer wants to install an IBM BladeCenter infrastructure but is concerned about the cost of the full fabric internal fibre switches. Consequently, the customer is considering an N_Port ID Virtualization (NPIV) capable switch. Which of the following should be mentioned to the customer regarding the NPIV switch?()

  • A、Youcan not use an NPIV switch in the same IBM BladeCenter chassis as a Cisco Intelligent Ethernet Switch
  • B、Using blade servers with the NPIV switch will require morefibre ports on the external fibre switch
  • C、Storage devices likeFibre Channel Tape and Disk cannot be attached to the NPIV Switch but must connect to a core fabric switch.
  • D、The NPIV switch will count against the number of domains in a fabric

正确答案:C

第10题:

A small business customer is interesting and requires some shared storage. They expect only 3-4 blades, but wise the storage they require 4 TB RAID 1+0. They also require Flash copy and remote mirroring. Which of the following will be an issue?()

  • A、FlashCopy is not supported on the DS3000
  • B、Remote mirroring is supported on the DS3000
  • C、FlashCopy is supported on the BladeCenter S RAIDed SAS Switch Modules
  • D、FlashCopy is not supported on BladeCenter S RAIDed SAS Switch Modules

正确答案:D