Changes may be requested by any

题目

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

  • A、executive IT manager
  • B、projectmanger
  • C、change control board
  • D、projectsponsor
参考答案和解析
正确答案:C
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

A.executive IT manager

B.project manger

C.change control board

D.project sponsor


正确答案:C
试题(73)分析
 项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。
参考答案
(73)C

第2题:

The government is asking for____ changes in both education and economy, but the people wonder whether the new changes would be of any good to them.

A、super

B、chimney

C、sweeping

D、ruin


正确答案:C

第3题:

● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.

(75)

A. proceedings

B. controls

C. forecasting’s

D. prelibations


正确答案:B

第4题:

During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.

A.proceedings

B.controls

C.forecasting's

D.prelibations


正确答案:B
解析:在一个项目的生命期内,有多种原因可以引起对需求的变更。当需要发生变更而工作正在进行时,可导致新的需求产生并迫使现有的需求发生变更。需要快速而有效地管理这些新的需求和新的变更。为了有效地分析这些变更的影响,必须确定每一个需求源,并记录变更的基本过程。无论如何,项目经理希望能追踪有关需求稳定性的、恰当的措施,以判断是否需要新的或修正的控制措施。

第5题:

management includes negotiating the terms and conditions in contracts and ensuring compliance with the terms and conditions,as well as documenting and agreeing on any changes or amendments that may arise during its implementation or execution

A.Contract

B.Document

C.Communication

D.Risk


正确答案:A
本题目翻译:干系人管理包括协商的条款和条件的合同,并确保遵守的条款和条件,以及记录和商定其实施或执行过程中可能出现的任何改变或修正。考察的是干系人管理。

第6题:

You will be informed about any subtle changes ________ .

A at the first opportunity

B for the first opportunity

C in the first opportunity

D on the first opportunity


参考答案A

第7题:

Network management helps you to(66)the strengths and weaknesses of your network, as well as determine any configuration changes that may be necessary. Any controlled changes to your network and its components-especially configurations, software and(67), can have an effect on its overall efficiency. To maintain control, you need the tools and knowledge to manage all activity that has the potential to affect your(68).

A.see

B.know

C.monitor

D.control


正确答案:C
解析:Monitor意为“监控”。

第8题:

Hearing problems may be alleviated by changes in diet and exercise habits.

A.removed

B.cured

C.worsened

D.relieved


正确答案:D
解析:本题考查的是对动词的认知。这句话的意思是:听力问题可由改变日常饮食和锻炼的习惯而缓解。本题考察对及物动词alleviate和其同义词的掌握。alleviate意为“减轻”。例如:We want to help alleviate the national food shortage.我们想帮助缓解国家粮食短缺的状况。同义词有relieve减轻、变小;palliate减轻、缓和;assuage缓和、减轻。所以选D。A.remove去掉、切除;B.cure治疗;C.worsen恶化。

第9题:

What are the characteristics of the process of documenting the layers of an existing network? ()

A. begins with gathering organizational input that may be inaccurate

B. begins with gathering organizational input that does not need to be supplemented by a network audit

C. requires a network audit to support some upgrade decisions

D. requires a network audit to support any network restructuring

E. provides reliable input for verifying network consistency

F. does not provide reliable input for designing changes


参考答案:A, D, E

第10题:

In the last paragraph,the author mainly intends to

A.list the necessary changes we ought to make

B.advise US to make any necessary changes

C.explain what changes can bring

D. explain the process of making changes


正确答案:B
概括文章最后一段可知,作者建议我们,改变无所谓大小,只要必要就需要改变。A项是对文章的片面理解;C项是文章的细节,不是段落的主旨。

更多相关问题