Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.( ) is a method that analyze a

题目
Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.( ) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

A.Cost-Benefit analysis
B.Control charts
C.Quality function deployment
D.Cost of quality analysis
参考答案和解析
答案:D
解析:
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


正确答案:B

第2题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第3题:

The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A . budget, schedule

B . quality requirements, schedule

C . size, type of industry

D . nature, size

E . project manager, sponsor


正确答案:D

 

第4题:

Performing( )involves monitoring specific project results to determine ifthey comply with relevant quality standards and identifying ways to eliminate causes ofunsatisfactory results。 A.quality planning B.quality assurance C.quality performance D.quality control


正确答案:D
执行质量控制(quality control)指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

第5题:

The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

A.Manage quality

B.Quality audit

C.Quality metrics

D.Quality improvement


正确答案:A

第6题:

● Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

(74)

A. quality planning

B. quality assurance

C. quality performance

D. quality control


正确答案:D

第7题:

● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

A.performance

B.process

C.product

D.object


正确答案:C

第8题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第9题:

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

A.work performance information

B.scope statement

C.change requests

D.process analysis


正确答案:B

第10题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

更多相关问题