单选题A customer needs a 2-way Xeon system today but plans on expanding to a 4-way early next year.  The customer is looking to limit the initial costs as much as possible but may not be as budget constrained next year.  Which of the following is the best so

题目
单选题
A customer needs a 2-way Xeon system today but plans on expanding to a 4-way early next year.  The customer is looking to limit the initial costs as much as possible but may not be as budget constrained next year.  Which of the following is the best solution to all the customer’s needs?()
A

An x445 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.

B

An x445 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.

C

An x366 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.

D

An x366 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of the following best describe the customer benefits of change management in the operate phase? Select exactly 1 answer(s) from the following:()。

  • A、reduce unnecessary disruption, delays, rework, and other problems by establishing test cases for use in verifying that the system meets operational, functional, and interface requirements
  • B、improve its ability to make sound financial decisions by developing a business case based on its business requirements and establishing a basis for developing a technology strategy
  • C、reduce operating costs and limit change-related incidents by providing a consistent and efficient set of processes
  • D、improve the return on investment and hasten migration by identifying and planning for necessary infrastructure changes and resource additions, as well as reduce deployment costs by analyzing gaps early in the planning process to determine what is needed to support the system

正确答案:C

第2题:

A frustrated and angry customer calls in with a system that does not work. Which of the following is the FIRST course of action for a technician to take?()

  • A、Transfer the customer to another technician, who can allocate more time to the issue.
  • B、Maintain a positive attitude and offer them the cheapest solution possible to satisfy them.
  • C、Listen to what the customer has to say and calmly recommend the best course of action.
  • D、Use technical language to demonstrate knowledge and expertise to the customer.

正确答案:C

第3题:

–I hear Sharon is planning to study in Germany next year.–().

A、That’s so exciting!

B、I don't know.

C、It is possible.

D、No, she will not.


参考答案:A

第4题:

A customer needs a 2-way Xeon system today but plans on expanding to a 4-way early next year.  The customer is looking to limit the initial costs as much as possible but may not be as budget constrained next year.  Which of the following is the best solution to all the customer’s needs?()

  • A、An x445 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.
  • B、An x445 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.
  • C、An x366 with 2 Xeon MP processors.  Plan on adding 2 more Xeon MP processors next year.
  • D、An x366 with 2 Xeon DP processors.  Plan on adding 2 more Xeon DP processors next year.

正确答案:C

第5题:

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

  • A、What are the plans for Disaster Recovery? 
  • B、What are the plans for data migration? 
  • C、Would iSCSI meet your needs? 
  • D、How much space is available in the current storage systems?

正确答案:B

第6题:

A customer has an 8-way p650 running an application for about 200 users.  In the past, the requiredamount of memory and processors has increased proportionally to the number of new users.  The customer plans to increase users by 10% each year for the next three years.  Next year, a database will be added to the workload to support the users directly rather than being on a separate machine. What is the most likely result of this projected growth?()

  • A、Disk usage will increase in proportion to memory.
  • B、The new database will demand much more memory.
  • C、Memory demand will increase 10% for the next year.
  • D、Processor demand will increase about 10% for the next year.

正确答案:B

第7题:

An IBM XIV system with nine modules and 2 TB disks is being proposed to a customer who needs to increase disk capacity in the data center. The customer is concerned about data growth andcost after the initial purchase. Which of the following factors of the solution should be stressed to the customer to address data growth?()

  • A、the XIV system can be scaled by the addition of modules
  • B、XIV offers thin provisioning for all available host operating systems
  • C、reduced operating costs will pay for another XIV system in less than two years
  • D、the management GUI allows the administrator tovirtualize the entire storage system quickly

正确答案:A

第8题:

An IBM XIV system with nine modules and 2 TB disks is being proposed to a customer who needs to increase disk capacity in the data center. The customer is concerned about data growth andcost after the initial purchase. Which of the following factors of the solution should be stressed to the customer to address data growth?()

A. the XIV system can be scaled by the addition of modules

B. XIV offers thin provisioning for all available host operating systems

C. reduced operating costs will pay for another XIV system in less than two years

D. the management GUI allows the administrator tovirtualize the entire storage system quickly


参考答案:A

第9题:

A customer requires a 2-way solution now that will be the easiest and least disruptive to upgrade to a 4-way in the future.  Which of the following solutions best matches these requirements?()

  • A、p630 2-way Active 2-way Inactive
  • B、p655 2-way Active 2-way Inactive
  • C、p5-520 2-way Active 2-way Inactive
  • D、p5-550 2-way Active 2-way Inactive

正确答案:D

第10题:

A customer is looking at an Oracle eBusiness solution. They would like to know what hardware they will need for the solution. They have some preliminary information from Oracle, including hardware requirements and specifics for their environment. Which of the following should be done next?()

  • A、Configure a 2 node x3950 X5 
  • B、Customer needs a System p server to support Oracle applications 
  • C、Download the Oracle eBusiness sizing questionnaire from IBM, fill out with customer and submit to IBM for System x sizing 
  • D、Configure a system that meets the minimum requirements

正确答案:C