There are six phases of the Cisco Lifecycle Services framework. During which of the following phases would the Acceptance Testing be developed and documented?()A、OperateB、DesignC、ImplementD、Prepare

题目

There are six phases of the Cisco Lifecycle Services framework. During which of the following phases would the Acceptance Testing be developed and documented?()

  • A、Operate
  • B、Design
  • C、Implement
  • D、Prepare
参考答案和解析
正确答案:B
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of these correctly identifies the six phases of the Cisco Lifecycle Services framework? ()

A. Prepare, Plan, Create, Implement, Operate, and Improve

B. Prepare, Plan, Design, Implement, Operate, and Optimize

C. Prepare, Plan, Design, Apply, Operate, and Manage

D. Prepare, Plan, Design, Implement, Operate and Manage


参考答案:B

第2题:

In Which of these phases are a customer’s business requirements identified and documented?()

  • A、plan
  • B、design
  • C、prepare
  • D、operate

正确答案:C

第3题:

Optimize is one of the six phases of the Cisco Lifecycle Services framework. Which of the following in the optimize phase allows you to assess the routing and switching system, as well as recommend actions, including optimizing device configurations, capacity planning, etc.?()

A. Security Assessment

B. Change Management

C. Technology Assessment

D. Operations Readiness Assessment


参考答案:C

第4题:

Which of these is the best definition of the Cisco Lifecycle Services approach? Select exactly 1 answer(s) from the following:()。

  • A、It defines the minimum set of services required to successfully deploy and operate a set of Cisco technologies
  • B、It determines how best to price Cisco products
  • C、It provides partners with a useful way to leverage Cisco resources
  • D、It consists of these phases: plan, deploy, support, and troubleshoot

正确答案:A

第5题:

At which stage of the Cisco Lifecycle Services approach would you test for system acceptance?()

  • A、 Preparation
  • B、 Planning
  • C、 Design
  • D、 Implementation
  • E、 Operation
  • F、 Optimization

正确答案:D

第6题:

In which of these phases is a customers current network infrastructure assessed?()

  • A、plan
  • B、design
  • C、implement
  • D、prepare

正确答案:A

第7题:

In which of the following phases can you ensure that the new Cisco Unified Communications solution is integrated without disrupting the existing network()

  • A、Operate
  • B、Plan
  • C、Deploy
  • D、Implement

正确答案:B

第8题:

In which phase is a systems acceptance test plan developed and documented? ()

A.Implement

B.Design

C.Prepare

D.Operate


参考答案:B

第9题:

In which of these phases are a customers technology strategy requirements identified and documented? Select exactly 1 answer(s) from the following:()。

  • A、Plan
  • B、design
  • C、prepare
  • D、operate

正确答案:C

第10题:

In which phase is a systems acceptance test plan developed and documented? ()

  • A、Implement
  • B、Design
  • C、Prepare
  • D、Operate

正确答案:B