To ensure quality, what is the maximum end-to-end transit time in milliseconds on a voice network?()
第1题:
What is the relative priority of project Cost, Schedule and Quality?
A . 1)Cost - 2)Schedule - 3)Quality
B . 1)Quality - 2)Schedule - 3)Cost
C . 1)Quality - 2)Cost - 3)Schedule
D . 1)Schedule - 2)Quality - 3)Cost
E . All are of equal priority
第2题:
130 What is the relative priority of project Cost, Schedule and Quality?
A. 1)Cost - 2)Schedule - 3)Quality
B. 1)Quality - 2)Schedule - 3)Cost
C. 1)Quality - 2)Cost - 3)Schedule
D. 1)Schedule - 2)Quality - 3)Cost
E. All are of equal priority
第3题:
100 % inspection of output is:
A . the best proven method to ensure quality
B . is expensive, ineffective approach to quality management
C . can never be, justified
D . can still leave some defects undetected
E . B and D only
第4题:
Beamforming通常用于保证『____』用户业务质量。(Beamforming is typically used to ensure the quality of 『____』user services .)
第5题:
● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
(73)
A. Quality assurance (QA)
B. Quality planning
C. Quality control (QC)
D. Quality costs
第6题:
41 In the project environment, the individual ultimately responsible for quality control is:
A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D. The project manager who has ultimate responsibility for the entire project.
E.the customer who must ensure that he is receiving a quality product from the vendor
第7题:
A.As far as l' m concerned
B.1 have no idea
C.1 don't agree with you
第8题:
In the project environment, the individual ultimately responsible for quality control is:
A . The line workers who must strive "to do things right the first time" to avoid quality problems.
B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.
C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.
D . The project manager who has ultimate responsibility for the entire project.
E . the customer who must ensure that he is receiving a quality product from the vendor.
第9题:
What can be inferred from Paragraph 4?
A. Unpackaged products are of bad quality.
B. Supermarkets care more about packaging.
C. It is improper to judge quality by packaging.
D. Other products are better packaged than food.
推理判断题。第四段讲述了人们对于包装不好的物品的固有认识,即:人们普遍认为包装不好的物品质量肯定差,所以C项应为正确答案。
第10题:
______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
A.euality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs