The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

题目
The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

(74) A. Product scope description

B. Project objectives

C. Product specification

D. The project scope statement


正确答案:D

第2题:

( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

A.Product scope description B.Project objectives C.Product specification D.The project scope statement


正确答案:D

第3题:

The()describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement

B.project requirement

C.project charter

D.product specification


参考答案:A

第4题:

A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.

A.Structure Chart

B.Organizational Structure

C.Work Breakdown Structure

D.Functional decomposition diagram


正确答案:C

第5题:

A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.

A.Structure Chart

B.Organizational Structure

C.Work Breakdown Structure

D.Functional decomposition diagram


正确答案:C

第6题:

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

(75)

A.independent resource

B.individual work load

C.work milestone

D.work package


正确答案:D
试题(75)分析
 WBS工作分解结构是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包work package的层次。
 独立资源independent resource、个人工作负荷individual work load以及工作里程碑work milestone都不是WBS分解的最小层级,因此选D。
参考答案
(75)D

第7题:

The(71)describes,in detail,the project's deliverables and the work required to create those deliverables.

A.project scope statement

B.project requirement

C.project charter

D.product specification


正确答案:A
解析:项目范围说明书详细描述了项目的可交付物以及为创建这些可交付物所需的工作。

第8题:

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

A.project elements

B.work drafts

C.work package

D.project deliverables


正确答案:D
解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

第9题:

______describes,in detail,the project's deliverables and the work required to create those deliverables.

A.Product scope description

B.Project objectives

C.Stakeholder Analysis

D.The project scope statement


正确答案:D
解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

第10题:

Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A.Integration

B.Scope

C.Configuration

D.Requirement


正确答案:B
解析:项目范围管理包括为确保项目包含且仅包含成功完成项目必需工作的所需过程。