In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
第1题:
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
(75)
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
第2题:
The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
第3题:
● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.
A.performance
B.process
C.product
D.object
第4题:
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
第5题:
The( )provides the project manager with the authority to apply organizational resources to project activities。
A.project management plan
B.project charter
C.project human resource plan
D.project stakeholders
第6题:
The inputs of developing project management plan do not include (72) .
A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
第7题:
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第8题:
● The inputs of developing project management plan do not include (72).
(72)
A. project charter
B. stakeholder management strategy
C. project scope statement
D. outputs from planning processes
第9题:
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。
第10题:
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A.performing organization
B.project management team
C.project
D.customer