The () describes, in detail, the project's deliverables and the work required to create those deliverables.
第1题:
A.project scope statement
B.project requirement
C.project charter
D.product specification
第2题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第3题:
The document authorizing functional areas to charge against the project is the:
A. Work authorization form
B. Scope baseline
C. Project charter
D. Management plan
E .Linear responsibility chart
第4题:
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria
A.work performance information
B.scope statement
C.change requests
D.process analysis
第5题:
( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.
A.Product scope description B.Project objectives C.Product specification D.The project scope statement
第6题:
● The document authorizing functional areas to charge against the project is the:
A Work authorization form
B Scope baseline
C Project charter
D Management plan
E Linear responsibility chart
第7题:
● (72)describes, in detail, the project’s deliverables and the work required to create those deliverables.
(72)
A. Product scope description
B. Project objectives
C. Stakeholder Analysis
D. The project scope statement
第8题:
61 The document authorizing functional areas to charge against the project is the:
A. Work authorization form.
B. Scope baseline
C. Project charter
D. Management plan
E. Linear responsibility chart
第9题:
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.
(74)
A.scope statement
B.activity list
C.project charter
D.project schedule
第10题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement