The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )

题目
The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )

A. Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
参考答案和解析
答案:B
解析:
项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到(75)。

A. 项目范围说明书 B. 项目管理计划

C. 项目预测 D. 项目章程
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.

A.integration

B.scope

C.process

D.charter


参考答案:A

该题的关键词为"unification、consolidation、articulation、integrativeactions",其语句结构为"(主语)includes(谓语)characteristics of unification,consolidation,articulation,andintegrativeactions",含义为"什么包括了统一、合并、沟通的特征以及集成活动",根据语句的含义容易识别为集成(或整体),对应的英文为Integration。

第2题:

● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

(74)

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities


正确答案:A
试题(74)分析
    项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
参考答案
    (74)A

第3题:

The sequential steps that define the process for successfully completing a project is:

A.Implementation Plan

B.a life cycle

C.Development Plan

D.a critical path

E.Management Plan


正确答案:B
B

第4题:

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities


正确答案:A
解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

第5题:

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

A.project elements

B.work drafts

C.work package

D.project deliverables


正确答案:D
解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

第6题:

● The sequential steps that define the process for successfully completing a project is:

A Implementation Plan

B a life cycle

C Development Plan

D a critical path

E Management Plan


正确答案:B

第7题:

● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

t

A.Integration

B.Scope

C.Configuration

D.Requiremen


正确答案:B

第8题:

115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan

B. a life cycle

C. Development Plan

D. a critical path

E. Management Plan


正确答案:B

第9题:

● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).

(71)

A. project elements

B. work drafts

C. work package

D. project deliverables


正确答案:D

第10题:

● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

(75)

A. Project Scope Statement

B. Project Management Plan

C. Forecasts

D. Project Charter


正确答案:B

试题(75)分析
  项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
  A.项目范围说明书                    B.项目管理计划
  C.项目预测                          D.项目章程
参考答案
  (75)B