第1题:
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter
该题的关键词为"unification、consolidation、articulation、integrativeactions",其语句结构为"(主语)includes(谓语)characteristics of unification,consolidation,articulation,andintegrativeactions",含义为"什么包括了统一、合并、沟通的特征以及集成活动",根据语句的含义容易识别为集成(或整体),对应的英文为Integration。
第2题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第3题:
The sequential steps that define the process for successfully completing a project is:
A.Implementation Plan
B.a life cycle
C.Development Plan
D.a critical path
E.Management Plan
第4题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第5题:
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
A.project elements
B.work drafts
C.work package
D.project deliverables
第6题:
● The sequential steps that define the process for successfully completing a project is:
A Implementation Plan
B a life cycle
C Development Plan
D a critical path
E Management Plan
第7题:
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
t
A.Integration
B.Scope
C.Configuration
D.Requiremen
第8题:
115 The sequential steps that define the process for successfully completing a project is: A. Implementation Plan
B. a life cycle
C. Development Plan
D. a critical path
E. Management Plan
第9题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第10题:
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
(75)
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter