The Perform. Integrated Change Control process is conducted from project lnception throug

题目

The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

A.change control board

B. project management office

C.project manager

D.configuration management officer

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

33 The purpose of configuration management is to:

A. insure drawings are updated

B. control change throughout the project

C. control change during the production only

D. generate engineering change proposals

E. inform. the project manager of changes


正确答案:B

第2题:

● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A Change the scope baseline

B Prepare a variance report

C Call a meeting of the configuration control board

D Change the project's objectives

E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第3题:

The purpose of configuration management is to:

A.insure drawings are updated

B.control change throughout the project

C.control change during the production only

D.generate engineering change proposals

E.inform. the project manager of changes


正确答案:B
B

第4题:

A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:D
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
  选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
  由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。

第5题:

● Scope management is:

A a project control function.

B employs change control.

C a work authorization process.

D considers Cost, Quality and Schedule.

E All of the above.


正确答案:E

第6题:

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


正确答案:E

第7题:

● The purpose of configuration management is to:

A insure drawings are updated

B control change throughout the project

C control change during the production only

D generate engineering change proposals

E inform. the project manager of changes


正确答案:B

第8题:

Scope management is:

A.a project control function.

B.employs change control.

C.a work authorization process.

D.considers Cost, Quality and Schedule.

E.All of the above.


正确答案:E
E

第9题:

● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

(73) A. change the scope baseline

B. contact the customer to determine if the change adds value

C. call a meeting of the change control board

D. change the project' s objectives


正确答案:B

第10题:

You develop a Web control. The Web control consists of labels and associated text boxes.You need to ensure that the Web control has both toolbox and visual designer support. What should you do?()

A. Add a Web Control Library project to your solution. Define a class that inherits from CompositeControl.

B. Add a Windows Control Library project to your solution. Define a class that inherits from UserControl.

C. Add a Web User Control to your project. Define a class that inherits from UserControl.

D. Add a Mobile Web User Control to your project. Define a class that inherits from MobileUserControl.


参考答案:A