The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

题目
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

A . Baseline costs

B . Budgeted costs.

C . Estimates upon completion costs

D . Scheduled costs

E . None of the above


正确答案:A

第2题:

Of the following, who has the ultimate responsibility for meeting project quality objectives?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner


正确答案:B

第3题:

Scope management is:

A.a project control function.

B.employs change control.

C.a work authorization process.

D.considers Cost, Quality and Schedule.

E.All of the above.


正确答案:E
E

第4题:

105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

A. Baseline costs

B. Budgeted costs.

C. Estimates upon completion costs

D. Scheduled costs

E. None of the above


正确答案:A

第5题:

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner


正确答案:B

第6题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第7题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第8题:

A comprehensive definition of scope management would be:

A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.

B.Approval of the scope baseline.

C.Approval of the detailed project charter.

D.Configuration control.

E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.


正确答案:A
A

第9题:

23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:

A. Baseline costs

B Budgeted costs.

C. Estimates upon completion costs

D. Scheduled costs

E. None of the above


正确答案:A

第10题:

● Scope management is:

A a project control function.

B employs change control.

C a work authorization process.

D considers Cost, Quality and Schedule.

E All of the above.


正确答案:E

更多相关问题