Resources cannot be shared with an i5 partition when it is put on a pSeries. The i5 partition needs its own 9411-100 tower because of IOP. V5R3 OS or later is required. There is a maximum of two partitions in a 590.
Resources cannot be shared between partitions when i5/OS is put on a pSeries. The i5 partition needs its own 9411-100 tower because of IOP. i5/OS can be at V5R2 or a V5R3. Currently only one i5 partition is allowed.
V5R3 is required for the i5 partitions. Virtual IO Server is not supported for the i5/OS partitions to share storage. Up to 10 i5 partitions per processor are allowed (a maximum of two processors for up to 20 partitions).
Processor and memory resources can be shared between AIX 5L, Linux and i5/os partitions. i5/OS needs to be at V5R3, and Virtual IO Server is not supported for the i5/OS partition to share storage. On a 1.65 GHz POWER5 p5 590 there is a maximum of one partition.
第1题:
Companycom has a 16 way 1.65 GHz p5 590 and wants to install a i5/OS partition on their server. The customer wants to keep installation costs to a minimum by sharing devices between all LPARs. Before the operating system can be installed in this partition, the customer was told that there are certain limitations that must be observed. What are these limitations?()
第2题:
Companycom has a p690 and currently has eight LPARs. They have purchased a p5 590 and wish to migrate their eight LPARs to the new server. The LPARs are running either AIX 5.2 or AIX 5.3 with the current maintenance. What is the LEAST disruptive method for this activity?()
第3题:
A customer has many RS/6000s and POWER4 systems running different AIX applications. What should the customer do to best position themselves for the migration to POWER5?()
第4题:
A customer wants to expand their current storage environment, but has floor space for only two machine frames or two racks. Their environment consists of IBM SAN Volume Controllers and IBM DS4000 systems. The DS4000 systems are at end of lease. The customer wants the maximum number of disks possible in two frames. Which of the following solutions is best for this customer?()
第5题:
A current Sun Solaris customer has just purchased their first p5 590. During the Solution Assurance, the backup requirements were discussed. Which of the following should be recommended to the customer with regards to restoring rootvg?()
第6题:
Companycom has a requirement to consolidate six web application servers. There is unused capacity of 2 CPUs on their new p5 570. Which operating systems and or features are required?()
第7题:
A Customer has a functional server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible. What method can achieve this?()
第8题:
A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server. What is the minimum PowerVM edition that supports the customer requirement?()
第9题:
An existing IBM customer has some iSeries servers in their environment. The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications. The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms. Which of the following will accomplish this?()
第10题:
Companycom has several AS/400 servers in their IT infrastructure running V5R2 that they wish to consolidate. The customer wants to simplify their environment and install i5/OS on a p5 590 with 16 1.65GHz processors and 20 i5/OS partitions. The customer plans to use the Advanced Power Virtualization to share their storage, processors, and memory. What considerations and limitations should be reviewed with the customer before the purchase?()