单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A Evaluate phase exit

题目
单选题
The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()
A

Evaluate phase exit milestones using sufficiency criteria

B

Flexible entry and exit criteria to minimize schedule delays

C

Quality measures reported only to the project steering committee

D

Many work teams with few members to maximize the number of deliverable hand-offs

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

In the project environment, the individual ultimately responsible for quality control is:

A . The line workers who must strive "to do things right the first time" to avoid quality problems.

B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D . The project manager who has ultimate responsibility for the entire project.

E . the customer who must ensure that he is receiving a quality product from the vendor.


正确答案:D

第2题:

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A Significantly reduce project risks

B eliminate project risks

C provide a rational basis for better decision making

D identify risks, their impact(s), and any appropriate responses

E None of the above.


正确答案:B

第3题:

The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A . budget, schedule

B . quality requirements, schedule

C . size, type of industry

D . nature, size

E . project manager, sponsor


正确答案:D

 

第4题:

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A.Project

B.project management team

C.performingorganization

D.customer


参考答案:C

该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

第5题:

59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A. Significantly reduce project risks

B. eliminate project risks

C. provide a rational basis for better decision making

D. identify risks, their impact(s), and any appropriate responses

E. None of the above


正确答案:B

第6题:

● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

(71)

A. project

B. project management team

C. performing organization

D. customer


正确答案:C

第7题:

41 In the project environment, the individual ultimately responsible for quality control is:

A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.

C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.

D. The project manager who has ultimate responsibility for the entire project.

E.the customer who must ensure that he is receiving a quality product from the vendor


正确答案:D

第8题:

Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

A.The project manager and project office personnel.

B.The project team and functional managers.

C.The project sponsor.

D.All of the above.

E.A and B only.


正确答案:E
E

第9题:

69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

A. budget, schedule

B. quality requirements, schedule

C. size, type of industry

D. nature, size

E. project manager, sponsor


正确答案:D

第10题:

● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

A The project manager and project office personnel.

B The project team and functional managers.

C The project sponsor.

D All of the above.

E A and B only.


正确答案:E