第1题:
In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
A unit price
B cost plus incentive fee
C cost plus fixed fee
D firm fixed price
E B and D only
第2题:
Which of the following types of contracts is equivalent to a cost plus contract:
A Fixed firm price
B Cost reimbursable
C Fixed price plus incentive fee
D progress payments
E All of the above.
第3题:
Which of the following control types has the highest risk to the owner:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
第4题:
A.XML
B.BLOB
C.DOUBLE
D.DBCLOB
第5题:
132 Which of the following contract types has the highest risk to the contractor:
A. Firm fixed price (FFP)
B. Time and material (T&M)
C. Cost plus fixed fee (CPFF)
D. Cost plus incentive fee (CPIF)
E. A and B only
第6题:
In which of the following contract types is it easier to change the scope of the contract:
A firm fixed price
B fixed price plus incentive fee
C cost plus percentage of cost
D letter contract
E None of the above.
第7题:
125 Which of the following types of contracts is equivalent to a cost plus contract:
A. Fixed firm price
B. Cost reimbursable
C. Fixed price plus incentive fee
D. progress payments
E. All of the above
第8题:
Which of the following types of contracts allows the owner to transfer risk to the contractor:
A cost plus incentive fee
B cost sharing
C firm fixed price
D cost plus fixed fee
E performance guarantees
第9题:
115 In which of the following contract types is it easier to change the scope of the contract:
A. firm fixed price
B. fixed price plus incentive fee
C. cost plus percentage of cost
D. letter contract
E. None of the above.
第10题:
A.CLOB
B.BLOB
C.Hierarchically
D.Rows and columns