单选题Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()A Enable remote commands on the HMC Configuration menu,then use ssh to logi

题目
单选题
Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()
A

Enable remote commands on the HMC Configuration menu,then use ssh to login to theHMC,enter su - root

B

Login to the HMC as hscpe and run pesh,using a temporary password from IBM Support,afterward, enter su - root

C

Login to the HMC as hscroot,then run pesh,using a temporary password from IBM Support, afterward,enter su - root

D

Enable remote commands on the HMC Configuration menu,then telnet in as hscroot,entersu - root

参考答案和解析
正确答案: A
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A pSeries technical specialist is performing a solutions assurance with a customer for a new single-frame 10-node p655 system being attached to a currently installed HMC.  Which of the following questions should be asked to gather all the required information to determine whether the p655 solution can connect to the HMC?()

  • A、Are there at least ten RS-232 ports available on the HMC?
  • B、Are there at least ten RS-422 ports available on the HMC?
  • C、Are there at least ten RS-232 and two RS-422 ports available on the HMC?
  • D、Are there at least two RS-232 and ten RS-422 ports available on the HMC?

正确答案:C

第2题:

Which port must be open on the HMC to allow remote web access?() 

  • A、22
  • B、80
  • C、443
  • D、8080

正确答案:C

第3题:

Which port must be open on the HMC to allow remoteweb access?()

A.22

B.80

C.443

D.8080


参考答案:C

第4题:

A system administrator is installing a p5 590 server with an HMC. After pulling the websm client down, it is not possible to connect to the HMC. The HMC can be pinged from the client. Which of the following settings should be verified next?()

  • A、The routes on the HMC
  • B、The firewall setting of the LAN adapter
  • C、The name resolution protocol on the p5 590 server
  • D、The subnet mask settings on the Ethernet adapters

正确答案:B

第5题:

Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()

  • A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. 
  • B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. 
  • C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. 
  • D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

正确答案:B

第6题:

Which of the following procedures will allow an operator to access an LPAR console session?()

  • A、Open a vterm from the VIO graphical interface to get the partition console.
  • B、Open a vterm from the ASMI graphical interface to get the partition console.
  • C、Start an ssh session to the HMC. Use the vtmenu command to select the desired LPAR.
  • D、Start an ssh session to the VIO. Use the vtmenu command to select the desired LPAR.

正确答案:C

第7题:

An administrator needs to recover an HMC due to a failed disk. The disk has been replaced, allowing the administrator to reinstall the HMC back to the required release of software. Backups of both the HMC Console Data and Upgrade Data are available. After reloading the HMC with the Recovery DVDs, what are the next steps to restore the HMC configuration?()

  • A、Use the 'HMC Management > Restore HMC Data' option to first restore just the HMC Data..
  • B、Use the 'HMC Management > Restore Upgrade Data' option to first restore just the Upgrade Data.
  • C、Use the 'HMC Management > Restore HMC Data' option to first restore the HMC Data and then the Upgrade Data.
  • D、Use the 'HMC Management > Restore Upgrade Data' option to first restore the Upgrade Data, and then the HMC Data.

正确答案:A

第8题:

An administrator has an existing HMC and POWER6 570 connected to a network switch.  The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()

  • A、An additional switch for the new HMc  
  • B、Asynchronous adapters on the new HMc
  • C、The two 570 servers are directly connected to the new HMc  
  • D、One 570 is directly connected to the new HMC and the other is directly connected to the existing HMc

正确答案:A

第9题:

The account executive is asking about post-sales support for a new p5 HMC.  They need the pSeries technical specialist to configure an HMC with software support for the customer.  Which of the following should the specialist include in the configuration?()

  • A、Supportline
  • B、ServiceSuite
  • C、Software Maintenance Agreement (SWMA)
  • D、Machine Control Program Remote Support Agreement (MCPRSA)

正确答案:D

第10题:

Which port must be open on the HMC to allow remoteweb access?()

  • A、22
  • B、80
  • C、443
  • D、8080

正确答案:C

更多相关问题