During the implement phase, systems acceptance testing does 

题目
单选题
During the implement phase, systems acceptance testing does which of the following for the customer? Select exactly 1 answer(s) from the following:()。
A

installation, configuration, and testing, as well as the commissioning of tools and processes in accordance with the operations implementation plan

B

provision of information regarding customer-specified design requirements and configuration

C

the migration of network services from an existing state to a future state in accordance with the migration plan

D

the provision of an objective means of measuring system operability and functionality

参考答案和解析
正确答案: D
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which of the following statements is correct?

A.The definition phase results in the Software Requirements Specification.

B.Testing is optional in software life cycle.

C.CASE tools can only aid in the design phase of a software life cycle.

D.A change during a later phase does not require the documentation of all earlier phases to be updated.


正确答案:A

第2题:

Many of the activities performed during the preliminary investigation are still being conducted in( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the ( )and must develop enough knowledge about the (3) and the existing systems to enable an effective solution to be proposed and implemented. Besides the ( )for process and data of current system, the deliverable from this phase also includes the ( )for the proposed system.

(3)应选( )。


A. harD.ware environment
B. testing environment
C. software environment
D.. business environment


答案:D
解析:
本题考查的是初步调研的相关知识,这个考点可以做个了解。经常考初步调研阶段的许多活动在分析阶段仍然要继续,而且会比以前更深入许多。在分析阶段,分析师必须要完全清楚最终蓝图并且掌握充分的业务环境和目前系统的商业环境,以使一个有效的解决方案被提出并且执行。除了当前系统的过程和数据的逻辑模型,这一阶段的产出物还包括建议系统的正式需求定义。73、A、硬件环境,B、测试环境,C、软件环境,D、商业环境

第3题:

The purpose of systems analysis phase is to build a logical model of the new system. The first step is( ), where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the( ). You use the fact-finding results to build business models, data and process models, and object models. The deliverable for the systems analysis phase is the( ), which describes management and user requirements, costs and benefits, and outlines alternative development strategies. The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase, you need to determine the( ), which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the( ), which is presented to management and users for review and approval.

A.System logical modelingB.use case modelingC.requirements modelingD.application modeling A.systems planning phaseB.systems modeling phaseC.systems analysis phaseD.systems design phase A.system charterB.system scope definitionC.system blueprintD.system requirement document A.application architectureB.system data modelC.system process modelD.implement environment A.system architecture descriptionB.system design specificationC.system technique architectureD.physical deployment architecture


正确答案:B,A,B,C,B

第4题:

During this phase,the analyst must must develop enough knowledge about the ( )and the existing systems to enable an effective solution to be proposed and implemented.

A.hardware environment
B.testing environment
C.software environment
D.business environment

答案:D
解析:
在这个分析阶段,系统分析师一定要充分掌握关于业务环境和现行系统的知识,以提交和实施一个有效的解决方案。
A.硬件环境 B.测试环境 C.软件环境 D.业务环境

第5题:

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

A.application architecture
B.system datA.model
C.system process model
D.implement environment

答案:C
解析:
翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(74) A.应用程序架构描述B.系统数据模型C.系统过程模型 D.实施环境参考答案:(74)C

第6题:

●In general,atypical (71) model is composed of several phases, such as requirements analysis phase, generaUdetailed design phase, implementation phase, system acceptance testing phase.

(71)

A. waterfall

B.incremental

C.spiral

D.prototyping


正确答案:A

第7题:

The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.

A.systems planning phase
B.systems modeling phase
C.systems analysis phase
D.systems design phase

答案:A
解析:
翻译:系统分析阶段的目的是建立新系统的逻辑模型,第一步就是进行(71),调查业务流程并记录新系统必须做哪些以满足用户需求。这一步是(72)的延续,可以使用调查结果构建业务模型,数据和流程模型以及对象模型。系统分析阶段的可交付成果是(73),它描述了管理和用户要求,成本和收益,还有可替代的方案。系统设计阶段的目的是创建一个能够满足系统所有需求文件要求的物理模型。 在系统设计阶段,需要确定(74),程序员通过系统过程模型把逻辑设计转换为程序模块和代码。该阶段的可交付成果是(75),提交给管理层和用户审查和批准。(72) A.系统计划阶段B.系统建模阶段C.系统分析阶段 D.系统设计阶段
参考答案:(72)A

第8题:

In which phase is a systems acceptance test plan developed and documented? ()

A.Implement

B.Design

C.Prepare

D.Operate


参考答案:B

第9题:

During this phase, the analyst must become fully aware of the ____ and must develop enough knowledge about the __请作答该选项__ and the existing systems to enable an effective solution to be proposed and implementeD.

A.hardware environment
B.testing environment
C.software environment
D.business environment

答案:D
解析:

第10题:

Which service component in the implement phase is typically performed prior to the handover of awireless solution to the customer’s operations organization?()

  • A、Systems Integration
  • B、Skill Assessment
  • C、Systems Acceptance Testing
  • D、Wireless Check
  • E、Project Close Out

正确答案:C