第1题:
The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Plannlng
B.Executing
C.Monitoring and Controlling
D.Closing
第2题:
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
第3题:
During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A.Ask the line manager to make the decision.
B.Ask the line manager to work with senior management to prioritize the work.
C.Ask your sponsor to meet with the line manager.
D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E.Prepare a purchase order to outsource the work.
第4题:
A、hadn t had completed
B、didn t have completed
C、couldn t have completed
D、cannot have completed
第5题:
A、have had worked
B、have been working
C、are working
D、work
第6题:
The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out
第7题:
●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.
(74) A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
第8题:
● The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.
第9题:
A、work out
B、work up
C、work in
D、work on
第10题:
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement