Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering var

题目
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the

A.project scope statement
B.statement of work
C.project management plan
D.project policy
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Cost management includes:

A . Cost estimating/forecasting.

B . Cost budgeting/cost control.

C . Cost applications.

D . All of the above.

E . A and B only.


正确答案:D

第2题:

144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

A. Overhead rates, labor rates and material costs.

B. Overhead rates, schedule slippages, and rework.

C. Rework, cost-of-living adjustments, and overtime.

D. Material costs, shipping cost, and scope changes.

E. Labor rates, material costs, and cost reporting


正确答案:A

第3题:

In a contract, the point of total assumption refers to the point where:

A . The customer incurs the total financial responsibility for each additional dollar spent.

B . The contractor incurs the total financial responsiblity for each dollar spent.

C . The schedule and cost variance are zero.

D . The customer will incur no further costs for the work the contractor performs in the completion of the contract.

E . B and D only.


正确答案:E

第4题:

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development


正确答案:D

第5题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


参考答案:B

第6题:

98 Cost management includes:

A. Cost estimating/forecasting.

B. Cost budgeting/cost control.

C. Cost applications.

D. All of the above.

E. A and B only


正确答案:D

第7题:

73 In a contract, the point of total assumption refers to the point where:

A. The customer incurs the total financial responsibility for each additional dollar spent.

B. The contractor incurs the total financial responsiblity for each dollar spent.

C. The schedule and cost variance are zero.

D. The customer will incur no further costs for the work the contractor performs in the completion of the contract.

E. B and D only


正确答案:E

第8题:

Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:

A . Overhead rates, labor rates and material costs.

B . Overhead rates, schedule slippages, and rework.

C . Rework, cost-of-living adjustments, and overtime.

D . Material costs, shipping cost, and scope changes.

E . Labor rates, material costs, and cost reporting.


正确答案:A

第9题:

● (73) is one of the techniques used for estimating activity durations.

(73)

A.Analogous Estimating

B.Precedence Diagramming Method (PDM)

C.Dependency Determination

D.Schedule network Templates


正确答案:A
试题(73)分析
    下列用于活动历时估算的技术是答案A类比估算法。
参考答案
    (73)A

第10题:

Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

A.expert judgment

B.analogous estimating

C.requiremen tstraceability matrix

D.three-point estimating


正确答案:C

更多相关问题