Project schedule management is made up of six management pro

题目
单选题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A

activity duration estimating, schedule developing, activity resource estimating

B

activity resource estimating, activity duration estimating, schedule development

C

schedule developing, activity resource estimating, activity duration estimating

D

activity resource estimating, schedule developing, activity duration estimating

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


正确答案:B
试题(71)分析
 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
 项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
 以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
参考答案
(71)B

第2题:

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

A.Developing project charter

B.Developing project management plan

C.Analyzing project risks

D.Monitoring and controlling project


正确答案:C

第3题:

Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A.activity duration estimating, schedule developing, activity resource estimating

B.activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


参考答案:B

第4题:

A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements list

A.Essences

B.Elements

C.Purposes

D. Issues


正确答案:B
本题目翻译:进度表是常用的项目规划和项目组合管理。按计划元素可能是密切相关的工作分解结构(WBS)的终端元素,工作的陈述,或合同数据要求清单。考察的是进度计划。

第5题:

In project time management processes,( )involves identifying and documenting the relationships between project activities.

A.activity definition

B.activity sequencing

C.schedule control

D.Schedule development


正确答案:B

第6题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

第7题:

● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .

(73)

A. measure, delay, record, distribute, analyze, and direct

B. plan, schedule, monitor, control, report, and forecast

C. promote, highlight, monitor, control, forecast, and report

D. emphasize, visualize, analyze, conceptualize, report, and record


正确答案:B

第8题:

● Scope management is:

A a project control function.

B employs change control.

C a work authorization process.

D considers Cost, Quality and Schedule.

E All of the above.


正确答案:E

第9题:

Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.

A.cost management planB.risk management planC.scope management planD.management schedule


正确答案:D

第10题:

The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.

A.goals

B.values

C.needs

D.Level


正确答案:C