A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work

题目
A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.

A.Essences
B.Elements
C.Purposes
D.Issues
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A.Time, schedule and cost.

B.Management coordination and organization structuring.

C.Work methods and accountability.

D.Quality of work.

E.Risk and impact decision-making.


正确答案:D
D

第2题:

● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A task

B level of effort

C sub-task

D project

E work package


正确答案:E

第3题:

When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A.task

B.level of effort

C.sub-task

D.project

E.work package


正确答案:E

第4题:

● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .

(72)

A.identifying individual tasks for a project

B.scheduling the start of tasks

C.scheduling the end of tasks

D.determining potential delays


正确答案:A

第5题:

● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A Time, schedule and cost.

B Management coordination and organization structuring.

C Work methods and accountability.

D Quality of work.

E Risk and impact decision-making.


正确答案:D

第6题:

The primary source document for establishing the content of the Project Status Report is:

A The project charter

B The Project Plan

C The ASTM Project Document Guide

D The summary work breakdown structure


正确答案:B

第7题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A

第8题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第9题:

The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


正确答案:C
挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

第10题:

● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.

(74)A.the project is ahead of its planned schedule

B.less work was completed than was planned

C.the cost overrun for work completed

D.the cost under-run of performance to date


正确答案:B

更多相关问题