题目
单选题
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has ( ) potential communication channels.
A

10

B

45

C

50

D

100

参考答案和解析
正确答案: D
解析: 10*9/2=45,参考答案:B
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.

A.10

B.45

C.50

D.100


参考答案:B

第2题:

System analysis is traditionally done top-down using structured analysis based on( ). Object-oriented analysis focuses on creation of models. The three types of theanalysis model are( ). There are two substages of object-oriented analysis.( )focuses on real-world things whose semantics the application captures. The object constructedin the requirement analysis shows the( )of the real-world system and organizes it intoworkable pieces.( )addresses the computer aspects of the application that are visible tousers. The objects are those which can be expected to vary from time to time quite rapidly.

A.functional decomposition B.object abstraction C.data inheritance D.information generalization A.function model,class model and state model B.class model,interaction model and state model C.class model,interaction model and sequence model D.function model,interaction model and state model A.Static analysis B.Semantic analysis C.Scope analysis D.Domain analysis A.static structure B.system components C.data flows D.program procedures A.Program analysis B.Function requirement C.Application analysis D.Physical model


正确答案:A,B,D,A,C

第3题:

"Paraphrasing" is most closely associated with which part of the communication process?

A encoding

B decoding

C barriers

D feedback

E None of the above.


正确答案:D

第4题:

● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

(75)

A.Cost-Benefit analysis

B.Control charts

C.Quality function deployment

D.Cost of quality analysis


正确答案:D
试题(75)分析
 质量分析成本Cost of quality analysis是对产品或服务进行需求一致性分析所产生的成本;
 成本效益分析Cost-Benefit analysi是通过比较项目的全部成本和效益来评估项目价值的一种方法;
 控制图Control charts是项目质量控制方法;
 质量功能展开Quality function deployment是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法
 因此,因此选D
参考答案
(75)D

第5题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

第6题:

●Models drawn by the system analysts during the process of the structured analysis are(72).

(72) A.PERTs

B.EMV

C.UMLs

D. DFDs


正确答案:D

第7题:

● In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project' s communications. According to Metcalfe's Law, a project with 10 stakeholders has ( 73 ) potential communication channels.

(73) A. 10

B. 45

C. 50

D. 100


正确答案:B

第8题:

Things that distort, distract, or muddle the communication process are called:

A noise

B selective filtering

C selective perception

D medium problems

E All of the above.


正确答案:A

第9题:

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。

A、Validate scope

B、Define scope

C、Control scope

D、Collect requirement


正确答案:C

第10题:

The development process in the software (74) involves four phases: analysis,design, implementation, and testing.

A.maintenance

B.lifecycle

C.programming

D.upgrading


正确答案:B
开发过程中的软件生命周期包括四个阶段:分析,设计,实现,测试。

更多相关问题