When implementing the project, we__________a lot of unexpect

题目
单选题
When implementing the project, we__________a lot of unexpected opposition from our colleagues.
A

run for

B

make against

C

run up against

D

make away with

参考答案和解析
正确答案: A
解析:
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

When subordinates know pertinent information that is not known by the project manager, the result is:

A Blindspot

B Facade

C region of influence

D Communication power base

E None of the above


正确答案:A

第2题:

● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A task

B level of effort

C sub-task

D project

E work package


正确答案:E

第3题:

A calendar that identifies when a project may be performed on an activity is called a:

A.Project calendar.

B.Resource calendar.

C.Milestone point.

D.Key point.

E.Work unit.


正确答案:A
A

第4题:

The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB

The most crucial time for project risk assessment is (75) .

A.when a problem surfaces

B.during the planning phase

C.during the close-out phase

D.after the project schedule has been published


正确答案:A
项目风险评估最重要的时间是:当问题呈现时在规划阶段在收尾阶段在项目进度发布后

第5题:

4. A foreigner can_______ a lot about Chinese when seeing Chinese movies.

A.learns

B.learn

C.knows

D.studies


正确答案:B
4.B【解析】情态动词后要用动词原形.

第6题:

11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only


正确答案:D

第7题:

● A calendar that identifies when a project may be performed on an activity is called a:

A Project calendar.

B Resource calendar.

C Milestone point.

D Key point.

E Work unit.


正确答案:A

第8题:

When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A . Reduce features and/or functionality

B . Increase risk.

C . Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D . All of the above.

E . A and B only


正确答案:D

第9题:

It's important for you to make a list of your tasks in order of _______ when you work on a project.

A、suggestion

B、goal

C、priority

D、tip


正确答案:C

第10题:

()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.

A.Identity risks

B.Control risks

C.Plan risk responses

D.Plan risk management


正确答案:B

更多相关问题