The communication management plan determines the information

题目
单选题
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
A

The communication management plan is contained in or is a subsidiary plan of, the project management plan.

B

The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.

C

The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

D

The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

75 Input into the Communications Management Plan includes the following information from the stakeholder analysis:

A. Information needs

B. Information content

C. Frequency of distribution

D. Method of distribution

E. All of the above


正确答案:E

第2题:

The failure of the plan was due ( ) bad management.

A、of

B、to

C、with


参考答案:B

第3题:

● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

A.Integration

B.Time

C.Planning

D.Communication


正确答案:D

第4题:

●The quality management plan should describe how the project management team will implement its quality (73).

(73) A. improvement

B. control

C. policy

D. information


正确答案:C

第5题:

The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


正确答案:B
制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

第6题:

The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.

B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.

C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


参考答案:C
沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D:沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。

第7题:

Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is(71) . It determines how the various results are computed by the product and presents this information in the form. of a(72) and associated scenarios. The second is(73) , which determines the classes and their attributes, then determines the interrelationships and interaction among the classes. The last step is(74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .

A.static modeling

B.dynamic modeling

C.use-case modeling

D.behavioral modeling


正确答案:C

第8题:

Input into the Communications Management Plan includes the following information from the stakeholder analysis:

A Information needs

B Information content

C Frequency of distribution

D Method of distribution

E All of the above


正确答案:E

第9题:

Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication


正确答案:D
项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

第10题:

An educational plan is an official document that authoritatively determines the content and principles of teaching and learning.()


参考答案:错误