翻译:duration

题目

翻译:duration

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

122 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

A. 8.0

B. 8.8

C. 9.1

D. 9.7

E. 10.5


正确答案:B

第2题:

● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating


正确答案:B
试题(71)分析
 项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
 项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历史估算、制定进度计划及进度控制六个步骤。
 以上六个步骤具有先后顺序,因此选择“活动的资源估算”activity resource estimating、“活动历史估算”activity duration estimating、制定进度计划schedule                 development,所以选B。
参考答案
(71)B

第3题:

Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

A . 0.5

B . 1

C . 1.8

D . 2.2

E . 2.8


正确答案:C

第4题:

● Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is (75) .

(75)

A.16 days

B.14 days

C.19 days

D.20 days


正确答案:C

第5题:

Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)

A.16days

B.14days

C.19days

D.20days


正确答案:C
解析:关键路径为最长时间的线路,3+6+7+1+2=19。

第6题:

Atoll的uSeR pRofile中主要对以下参数进行设置:()

A.SeRviCe、teRmiNAl、CAll/houR、duRAtioN、UL/DLvolume

B.CAll/houR、duRAtioN、UL/DLvolume

C.SeRviCe、teRmiNAl

D.SeRviCe、teRmiNAl、CAll/houR、duRAtioN


参考答案:A

第7题:

如果UE收到DRX Command的MACCE后,以下描述正确的是()。

A.停止Duration Timer

B.启动Duration Timer

C.启动drx-Retransmission Timer

D.停止drx-Retransmission Timer


正确答案:A

第8题:

Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

A . 8

B . 8.8

C . 9.1

D . 9.7

E . 10.5


正确答案:B

第9题:

下列哪个方法可以倒着播放一段影片?()

A.Speed/Duration对话框输入正值

B.Speed/Duration对话框中选择Reverse Speed选项

C.Rate Stretch Tool

D.Backwards特效


答案B

第10题:

短SCH Duration的好处有()。

A.BS有较多的机会来调整数据传输的速率

B.如果数据包长度比较短时,采用短的Duration,传输效率更高

C.TCP性能更加优越


参考答案:A, B, C

更多相关问题