第1题:
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第2题:
3 Project tradeoffs are usually made by comparing _____ and constraints.
A. Time, cost, and quality
B. Time, risk, and quality
C. Risk, quality, and manpower availability
D. Cost, quality, and technical performance
E. Cost, quality, and risk
第3题:
Project trade-offs vary between
A . risk, cost and schedule.
B . direct cost, indirect cost, and resource availability
C . quality, schedule and time
D . cost, quality and schedule
E . contract terms, scope and budget
第4题:
● (74) is primarily concerned with defining and controlling what is and is not included in the project.
(74)
A. Project Time Management
B. Project Cost Management
C. Project Scope management
D. Project Communications Management
第5题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第6题:
Scope management is:
A.a project control function.
B.employs change control.
C.a work authorization process.
D.considers Cost, Quality and Schedule.
E.All of the above.
第7题:
● Project tradeoffs are usually made by comparing _____ and constraints.
A Time, cost, and quality
B Time, risk, and quality
C Risk, quality, and manpower availability
D Cost, quality, and technical performance
E Cost, quality, and risk
第8题:
Project tradeoffs are usually made by comparing _____ and constraints.
ATime, cost, and quality
BTime, risk, and quality
CRisk, quality, and manpower availability
DCost, quality, and technical performance
ECost, quality, and risk
第9题:
● Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
第10题:
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.
(71)
A. Quantitative Risk Analysis
B. Qualitative Risk Analysis
C. Enterprise Environmental Factors
D. Risk Management Plan