Configure the IP address through the first client partition.
Configure the IP address through the ASMI menus.
Configure the POWER5 service processor for DHCP from the HMC DHCP server.
Configure the HMC to use the default IP address on the service processor when acquiring the managed server.
第1题:
Company.com has recently received a new p5-570 in the data center and intends to Micro-Partition the server. In which order should installation steps be taken?()
第2题:
Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
第3题:
A customer has an existing high availability SAN environment with CLARiiON, which has been stable for 16 months. They have recently experienced several outages with their current storage systems. They need to purchase additional storage and have asked about tier 1 storage. They are concerned with connecting their existing storage and servers without trouble.Which resource should be consulted while developing the solution options?()
A. Disk Magic
B. TPC for Data
C. CLARiiON Procedure Generator
D. System Storage Interoperability Center
第4题:
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()
第5题:
A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()
第6题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第7题:
ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()
第8题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第9题:
Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()
第10题:
ompany.com has recently received a new p5-570 in the data center and wants to connect it to an existing HMC environment where each of the existing POWER5 servers has been assigned a static IP address. Which of the following actions should the technical specialist perform to set the service processor network address for a static IP?()