WebLogic Node Manage

题目

WebLogic Node Manager can be used to manage the life cycle of WebLogic servers. WebLogic Node Manager is installed and started ().

  • A、Per Machine
  • B、Per Domain
  • C、Per Managed Server
  • D、Per Admin Server
参考答案和解析
正确答案:A
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

在一个Weblogic典型的生产环境中,()管理着应用。

  • A、Node服务器
  • B、Administration服务器
  • C、Managed服务器
  • D、Configuration服务器

正确答案:C

第2题:

Company.com has a three-node cluster (Node ’A’, Node ’B’, and Node ’C’) with three resource  Groups (rg1, rg2, and rg3). Node ’A’ has twice as many CPUs and twice as much memory as the two test add development Nodes ’B’ and ’C’. During normal production processing, all resource groups are active on Node ’A’.  What is most efficient way to configure the cluster to manage the workload?()   

  • A、 Use thee cascading resource groups where ’rg1’ and ’rg2’ fallover to Node ’B’ and ’rg3’ falls over to Node ’C’
  • B、 Use Dynamic Node Priority resource groups with a priority chain consisting of Node ’A’ then Node ’B’ then Node ’C’
  • C、 Use three rotating resource groups with ’rg1’ and ’rg2’ falling over to node ’B’ and ’rg3’ falling over to Node ’C’
  • D、 Upgrade Nodes ’B’ and ’C’ to be equal to Node ’A in CPU and memory resources to enable the cluster to synchronize three resource groups

正确答案:A

第3题:

下面哪个不属于weblogic的概念 ()

A. 概要文件profile

B. domain

C. cluster

D. node


参考答案A

第4题:

You want to create a WebLogic domain in a production environment. Which three actions should  you perform?()

  • A、Use a multinode WebLogic domain.
  • B、Use a single-node WebLogic domain. 
  • C、Use clusters.  
  • D、Refrain from using clusters.  
  • E、Install WeLogic in production mode with CA signed certificates.

正确答案:A,C,E

第5题:

An administrator has a two node cluster, Node1 and Node2, running resource group rg1. The resource groupis active on Node1. The administrator stopped cluster services and unmanaged the resource group on Node1to work on a problem. Now the administrator needs to move rg1 to Node2. Which of the following will achievethis?()

  • A、Perform a clstart on Node1 with ’Manage Resource Groups’ set to ’Manually’ and select the destination ofNode2
  • B、Perform a resource group move operation from Node1 to Node2 and select the option to ’Re-manageResource Groups’ set to ’Automatically’
  • C、Perform a clstop on Node1 with option to move resource groups, this will release the resource group fromNode1 and accquire the resource group on Node2.
  • D、Perform a clstart on Node1 with ’Manage Resource Groups’ set to ’Automatically’, then perform a resourcegroup move operation to move rg1 from Node1 to Node2

正确答案:D

第6题:

Weblogic集群启动顺序正确的是()

  • A、manage、proxv、admin
  • B、proxy、admin,manage
  • C、proxy、manage、admin
  • D、admin、proxy、manage

正确答案:D

第7题:

下面哪个不属于weblogic的概念()

  • A、domain
  • B、cluster
  • C、概要文件profile
  • D、node

正确答案:C

第8题:

Weblogic为了实现管理互动,每个域都需要它自己的()。

  • A、Administration服务器
  • B、Configuration程序助理
  • C、Ant Task
  • D、Node服务器

正确答案:A

第9题:

An HACMP cluster has three nodes of unequal size. The largest node is Node ’A’. The primary application on Node ’A’ has two components. One component is memory intensive, the other is IO intensive. Nodes ’B’ and ’C’ are running web servers and databases that access information produced by applications on Node ’A’. The customer requires the most performance from the primary application and wants all nodes available for fallover processing.  Which of the following is the best solution for meeting the customer requirements?()  

  • A、 Use nodes of equal size.
  • B、 Create multiple resource groups and use loadlever.
  • C、 Use dynamic node priority to manage resource groups.
  • D、 Use an ordered list to manage resource group fallover.

正确答案:C

第10题:

Node Manager is a WebLogic Server () that enables you to start, shut down, and restart Administration Server and Managed Server from a remote location.

  • A、 Instance
  • B、 Utility
  • C、 Destination
  • D、 Ouster

正确答案:B

更多相关问题