第1题:
A.project scope statement
B.project requirement
C.project charter
D.product specification
第2题:
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)
A.independent resource
B.individual work load
C.work milestone
D.work package
第3题:
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)
A. work performance information
B. scope statement
C. change requests
D. process analysis
第4题:
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)
(74)
A. Scope Planning
B. Scope Verification
C. Scope Change Control
D. Scope Definition
第5题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第6题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第7题:
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria
A.work performance information
B.scope statement
C.change requests
D.process analysis
第8题:
A.independentresource
B.individualworkload
C.workmilestone
D.workpackage
第9题:
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A.work performance information
B.scope statement
C.change requests
D.process analysis
第10题:
()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.
A.The project charter
B.The project scope statement
C.The WBS dictionary
D.The activity list