● Which of the following is not part of the quality assurance process?(73) (73)A.Operation

题目

● Which of the following is not part of the quality assurance process?(73)

(73)

A.Operational definitions

B.Quality policy

C.Quality audits

D.Quality improvement

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


正确答案:B

第2题:

●Which of the following statements describe(s)the properties of a purely segmented memory system? (73) .

Ⅰ.It suffers from internal fragmentation

Ⅱ.It permits implementation of virtual memory

Ⅲ.It divides memory into units of equal size

(73) A.Ⅰ only

B.Ⅲ only

C.Ⅱ only

D.Ⅰ andⅢ


正确答案:C
【解析】略。

第3题:

The key ingredient to a successful quality management program are _____.

A . management's quality philosophy, operational quality assurance and operational quality control.

B . quality evaluation methods and functional quality integrators.

C . technical quality administration, the technical quality specifications, and the quality process review.

D . quality evaluation methods, quality progress reviews and the technical quality specifications.

E . All of the above.


正确答案:A

第4题:

30 Which of the following is not part of the acquisition process:

A. source selection

B. invitation to bid

C. contract award

D. notice to proceed

E. All of the above are parts of the acquisition process


正确答案:D

第5题:

73 Which one of the following is not an acquisition method?

A. advertising

B. invitation

C. negotiation

D. purchase

E. all are acquisition methods


正确答案:A

第6题:

Which of the following is not part of the acquisition process:

A source selection

B invitation to bid

C contract award

D notice to proceed

E All of the above are parts of the acquisition process.


正确答案:D

第7题:

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner


正确答案:B

第8题:

Of the following, who has the ultimate responsibility for meeting project quality objectives?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner


正确答案:B

第9题:

87 The key ingredient to a successful quality management program are _____.

A. management's quality philosophy, operational quality assurance and operational quality control. B. quality evaluation methods and functional quality integrators.

C. technical quality administration, the technical quality specifications, and the quality process review. D. quality evaluation methods, quality progress reviews and the technical quality specifications.

E. All of the above


正确答案:A

第10题:

● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

(73)

A. Quality assurance (QA)

B. Quality planning

C. Quality control (QC)

D. Quality costs


正确答案:A

更多相关问题