多选题Using the Tivoli Dynamic Workload Console, what are two ways to  change the priority of a job?()AOpen the Set Priority panel from the job properties.BChange the priority of the job stream that contains the job.CSelect the corresponding action from the 

题目
多选题
Using the Tivoli Dynamic Workload Console, what are two ways to  change the priority of a job?()
A

Open the Set Priority panel from the job properties.

B

Change the priority of the job stream that contains the job.

C

Select the corresponding action from the Monitor jobs task panel.

D

Open the job stream properties and drill down to the job priority  panel.

E

The priority of a job can only be changed from the Workload  Designer.

参考答案和解析
正确答案: A,C
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Youexecutedthefollowingcode:BEGINDBMS_SCHEDULER.SET_ATTRIBUTE(NAME=>’JOB_A’,ATTRIBUTE=>’JOB_PRIORITY’,VALUE=>7);END;/Afteranalyzingtheabovecode,whatconclusionwillyoudraw?()

A.Thecodewillbeexecutedsuccessfully.

B.ThecodewillnotbeexecutedsuccessfullybecausethevalueoftheVALUEparametermustbe1,2,or3.

C.ThecodewillnotbeexecutedsuccessfullybecausethevalueoftheVALUEparametermustrangebetween1and5.

D.ThecodewillnotbeexecutedsuccessfullybecausenoSET_ATTRIBUTEprocedureexistsintheDBMS_SCHDULERpackage.


参考答案:C

第2题:

You notice that the elapsed time for an important database scheduler Job is unacceptably long.The job belongs to a scheduler job class and window.Which two actions would reduce the job‘s elapsed time?()

A. Increasing the priority of the job class to which the job belongs

B. Increasing the job‘s relative priority within the Job class to which it belongs

C. Increasing the resource allocation for the consumer group mapped to the scheduler job‘s job class within the plan mapped to the scheduler window

D. Moving the job to an existing higher priority scheduler window with the same schedule and duration

E. Increasing the value of the JOB_QUEUE_PROCESSES parameter

F. Increasing the priority of the scheduler window to which the job belongs


参考答案:B, C

第3题:

Protecting the confidentiality, integrity and availability of these information resources is a priority and a job responsibility for all employees at all levels of the company.


正确答案:对于公司中各个层次的雇员来讲,保护这些信息资源的机密性、完整性和有效性都是需要优先考虑的,是工作责任。

第4题:

Using Job Scheduling Console, how can the external successor chain  be viewed when a job needs to be canceled?()

  • A、 using the Hyperbolic Viewer
  • B、 opening the Impact view and displaying the successors
  • C、 opening the Job Stream Instance editor for its Job Stream Instance
  • D、 opening the Dependencies window and drilling down to the successors

正确答案:B

第5题:

You add an Online Responder to an Online Responder Array. You need to ensure that the new  Online Responder resolves synchronization conflicts for all members of the Array.     What should you do()

  • A、From Network Load Balancing Manager, set the priority ID of the new Online Responder to 1.
  • B、From Network Load Balancing Manager, set the priority ID of the new Online Responder to 32.
  • C、From the Online Responder Management Console, select the new Online Responder, and then select Set as Array
  • D、From the Online Responder Management Console, select the new Online Responder, and then select Synchronize

正确答案:C

第6题:

When setting arguments for a job, which procedure do you use for types that cannot be implicitly converted to and from a VARCHAR2 datatype?()

A. SET_JOB_ARGUMENT_VALUE

B. SET_JOB_VALUE_ANYDATA

C. SET_JOB_ANYDATA_VALUE

D. SET_SPECIAL_JOB_VALUE

E. SET_JOB_ANYTYPE_VALUE


参考答案:C

第7题:

How can a Job with EXEC as Internal Status be stopped in the Job Scheduling Console?()

  • A、 select Kill from the menu
  • B、 select Release from the menu
  • C、 select Cancel Job from the menu
  • D、 select Cancel Pending from the menu

正确答案:A

第8题:

Considerthefollowingcodesnippet:BEGINDBMS_SCHEDULER.SET_ATTRIBUTE(name=>,,lne_job1,attribute=>,,job_priority,value=>1);END;/Ifthiscodewereexecuted,whichofthefollowingstatementswouldbetrue?()

A.Thepriorityofthelne_job1jobwouldbesetto1.

B.Thelne_job1jobwouldbeexecutedsynchronously.

C.Thelne_job1jobwouldrunimmediatelyintheuserscurrentsession.

D.Thelne_job1jobwouldretainitscurrentpriority.

E.Thejobwillimmediatelytakepriorityoverallrunningjobs.


参考答案:A

第9题:

Using the Tivoli Dynamic Workload Console, what are two ways to  change the priority of a job?()

  • A、 Open the "Set Priority" panel from the job properties.
  • B、 Change the priority of the job stream that contains the job.
  • C、 Select the corresponding action from the Monitor jobs task panel.
  • D、 Open the job stream properties and drill down to the job priority  panel.
  • E、 The priority of a job can only be changed from the Workload  Designer.

正确答案:A,C

第10题:

An IBM Tivoli Workload Scheduler administrator finds that most of  the job streams are carried forward during each production day.  Which  action should the administrator take to ensure that only a  few job streams need to be carried forward? ()

  • A、 change start of day
  • B、 disable the Carry Forward option
  • C、 cancel all job streams before start of day
  • D、 Administrator does not have to take any action

正确答案:A

更多相关问题