单选题A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()A Build the logical partition in

题目
单选题
A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()
A

Build the logical partition infrastructure based on 6 or more VLANs.

B

Build the logical partition infrastructure based on two or more IVEs.

C

Build the logical partition infrastructure based on Partition Mobility.

D

Build the logical partition infrastructure based on redundant VIO Servers.

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer has a 32-core Power 770 with 4 AIX partitions and 2 IBM i partitions. They want to improve network availability and allow for concurrent maintenance. What will support the customer requirement at least cost?()

  • A、Build the logical partition infrastructure based on 6 or more VLANs.
  • B、Build the logical partition infrastructure based on two or more IVEs.
  • C、Build the logical partition infrastructure based on Partition Mobility.
  • D、Build the logical partition infrastructure based on redundant VIO Servers.

正确答案:D

第2题:

A customer has two Power 770 systems with 4 enclosures each.  Thirty two cores and 1TB of memory are activated on each system.  Each system has 3 database partitions and each partition has 10 cores and 300GB of memory.   Which solution will provide automated recovery of unplanned outages at least cost?()

  • A、Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failure
  • B、Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occurs
  • C、Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHA
  • D、Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover

正确答案:B

第3题:

A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()

  • A、Upgrade OS to AIX 5.2.
  • B、Implement Micro-Partitioning.
  • C、Upgrade HMC to support POWER5.
  • D、Install Partition Load Manager.

正确答案:A

第4题:

A customer has systems with AIX 6.1 and 5.3 distributed across two data centers located 8km apart. They want to implement high availability with automated application restart and synchronous data replication between the IBM Systems Storage DS8700 systems which are installed in each datacenter. Which solution addresses the customer requirements?()

  • A、Use the Geographic Logical Volume Manager (GLVM) for MetroMirror, and Live Partition Mobility to automate partition migration upon failure
  • B、Use MetroMirror for the AIX volumes and High Availability Disaster Recovery (HADR) to automate partition migration and restart upon failure.
  • C、Use the Geographic Logical Volume Manager (GLVM) for MetroMirror to replicate the data between the two sites and automate application recovery.
  • D、Use MetroMirror for the AIX volumes, and PowerHA SystemMirror Enterprise Edition to automate failover of MetroMirror pairs and automate application recovery.

正确答案:D

第5题:

Companycom has several AS/400 servers in their IT infrastructure running V5R2 that they wish to consolidate. The customer wants to simplify their environment and install i5/OS on a p5 590 with 16 1.65GHz processors and 20 i5/OS partitions. The customer plans to use the Advanced Power Virtualization to share their storage, processors, and memory. What considerations and limitations should be reviewed with the customer before the purchase?()

  • A、Resources cannot be shared with an i5 partition when it is put on a pSeries. The i5 partition needs its own 9411-100 tower because of IOP. V5R3 OS or later is required. There is a maximum of two partitions in a 590.
  • B、Resources cannot be shared between partitions when i5/OS is put on a pSeries. The i5 partition needs its own 9411-100 tower because of IOP. i5/OS can be at V5R2 or a V5R3. Currently only one i5 partition is allowed. 
  • C、V5R3 is required for the i5 partitions. Virtual IO Server is not supported for the i5/OS partitions to share storage. Up to 10 i5 partitions per processor are allowed (a maximum of two processors for up to 20 partitions). 
  • D、Processor and memory resources can be shared between AIX 5L, Linux and i5/os partitions. i5/OS needs to be at V5R3, and Virtual IO Server is not supported for the i5/OS partition to share storage. On a 1.65 GHz POWER5 p5 590 there is a maximum of one partition.

正确答案:C

第6题:

A small IT department is deploying Power 720 servers exploiting virtualization technologies.  Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()

  • A、AIX Basic Edition
  • B、AIX Express Edition
  • C、AIX Standard Edition
  • D、AIX Enterprise Edition

正确答案:C

第7题:

A customer has a key application running in a logical partition on a POWER5 system. The customer wants the ability to run the application with minimal down time using Live Partition Mobility.  Which of the following is the minimum PowerVM edition and hardware configuration that will support the customer requirement?()

  • A、 PowerVM Standard Edition on POWER6 hardware
  • B、 PowerVM Standard Edition with POWER5 hardware 
  • C、 PowerVM Enterprise Edition with POWER6 hardware
  • D、 PowerVM Enterprise Edition with POWER5 hardware

正确答案:C

第8题:

A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()

  • A、 PowerVM Lx86
  • B、 PowerVM Express Edition
  • C、 PowerVM Standard Edition
  • D、 PowerVM Enterprise Edition

正确答案:C

第9题:

A customer wants to run DB2 on a Power 780 with uncapped partitions. They have licensed DB2 for 32 of the 64 active cores, and will use it in multiple partitions.   How can the customer ensure that the number of licenses purchased for DB2 is not exceeded?()

  • A、Create a 32-core shared processor pool for the DB2 partitions.
  • B、Limit the number of virtual processors on each DB2 partition to 32.
  • C、Use the IBM License Metric Tool to dynamically manage DB2 usage in the partitions.
  • D、Set the ‘Desired Processing Units’ in each DB2 partition profile so that the sum of all partitions equals 32.

正确答案:A

第10题:

A customer is adding a new p5 machine to their environment.  The machine will host several DB2 partitions running AIX 5.2.  They currently have two SAN directors and an IBM ESS.  The SAN design allows for concurrent maintenance.  What is required on each partition to attach to the SAN?()

  • A、A minimum of two HBAs; the customer will need to download SDD
  • B、A minimum of four HBAs; the customer will need to download SDD
  • C、A minimum of two HBAs; the customer will need to configure MPIO
  • D、A minimum of four HBAs; the customer will need to configure MPIO

正确答案:A