单选题A customer has recently purchased some IBM x445 servers running Red Hat Enterprise AS 3 and wants to connect them to their existing EMC Clarion SAN controller.  Which of the following steps must be taken in order to validate the solution?()A Download t

题目
单选题
A customer has recently purchased some IBM x445 servers running Red Hat Enterprise AS 3 and wants to connect them to their existing EMC Clarion SAN controller.  Which of the following steps must be taken in order to validate the solution?()
A

Download the latest drivers from EMC for Red Hat Advanced Server.

B

Ensure that the EMC storage server is configured properly and has the latest firmware levels.

C

Verify the equipment is on the ServerProven list and complete a Solution Assurance Review (SAR).

D

Ensure that the systems are connected to the EMC SAN controller.

参考答案和解析
正确答案: C
解析: 暂无解析
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

CIOs and their staff have very little experience architecting or designing solutions to support unknown workloads. As executives focus on compliance issues, more systems must be architected to align with emerging or poorly defined requirements. If the customer prefers an integrated solution physically consolidated in a scalable, single framework that can connect to an enterprise class storage area network,  what solution would you recommend?()

  • A、Multiple 1U and 2U servers equipped with FC HBAs to connect to the enterprise SAN
  • B、Single 3U/4U servers expandable to 32-way equipped with FC HBAs to connect to the enterprise SAN
  • C、BladeCenter, expandable to 14 blades equipped with FC HBAs, and redundant 20-port FC SAN Switch modules to connect to enterprise SAN
  • D、IBM 1350 Cluster equipped with FC HBAs to connect to enterprise SAN

正确答案:C

第2题:

A customer has an existing SP system and needs to add cards to some of the nodes.  Which of the following applications must be used to configure the upgrade?()

  • A、MRPDPlus tool
  • B、Inventory Services
  • C、PCRS6000 Portable Configurator
  • D、eConfig - IBM Configurator for e-Business

正确答案:C

第3题:

An EMC customer is interested in storage virtualization. The IBM storage specialist has anappointment to discuss the SAN Volume Controller. Before making the call, which EMC productshould the storage specialist review?()

  • A、 VNX 
  • B、 VPLEX
  • C、 V-Series 
  • D、 USP-V

正确答案:B

第4题:

An existing IBM customer has some iSeries servers in their environment.  The customer is adding an x366 server with an RSA-II installed for their Microsoft Client/Server applications.  The customer wants to consolidate the storage and centralize the backup of the iSeries and xSeries platforms.  Which of the following will accomplish this?()

  • A、Share the data over the Ethernet LAN.
  • B、Install the IXA Adapter in the iSeries server.
  • C、Install the IXA Adapter in the xSeries server.
  • D、Attach both servers to an IXS switch.

正确答案:C

第5题:

An IBM Business Partner suggests an IBM System Storage DS8000 to a customer with a SAN   that is now configured with an EMC Symmetrix subsystem disk.  The customer wants to determine if new HBAs and software upgrades are needed on the servers if the EMC storage is replaced by the DS8000 What document must be carefully read to help address the customer’s concerns()

  • A、IBM System Storage DS8000: Host Systems Attachment Guide
  • B、DS8000 Interoperability Matrix
  • C、IBM System Storage DS8000: Introduction and Planning Guide
  • D、IBM System Storage Solution Handbook

正确答案:B

第6题:

A customer recently purchased a new x3550 M3 server and one of the hard drives has failed. The customer has a standard warranty. They called you asking for a replacement. Which action should the customer take?()

  • A、Contact the IBM FTSS to replace the drive
  • B、Contact the IBM CSR or SSR to replace the drive
  • C、Order a replacement drive
  • D、Contact IBM Service

正确答案:B

第7题:

A customer has recently purchased some IBM x445 servers running Red Hat Enterprise AS 3 and wants to connect them to their existing EMC Clarion SAN controller.  Which of the following steps must be taken in order to validate the solution?()

  • A、Download the latest drivers from EMC for Red Hat Advanced Server.
  • B、Ensure that the EMC storage server is configured properly and has the latest firmware levels.
  • C、Verify the equipment is on the ServerProven list and complete a Solution Assurance Review (SAR).
  • D、Ensure that the systems are connected to the EMC SAN controller.

正确答案:C

第8题:

A company wants to consolidate 20 existing dual processor Pentium III servers, all running a web server application on Windows Server 2003.  They are considering consolidating to a single x445 running VMWare ESX.  Which TWO of the following questions will provide enough information to determine the correct processor configuration?()

  • A、Do the web servers require SMP capability?
  • B、Is the web content static or dynamic information?
  • C、What is the average CPU utilization of the existing web servers?
  • D、Will the servers need a SCSI or Fibre Channel storage solution?
  • E、What are the expected growth rates for the web servers?

正确答案:C,E

第9题:

A customer wants to integrate an x445 running SuSE with their existing EMC storage infrastructure.  Which of the following tasks needs to be done to ensure that the solution will work properly?()

  • A、Ensure that the EMC storage is listed on the IBM Server Proven website
  • B、Ensure that the x445 is listed on the EMC Hardware Compatibility website
  • C、Ensure that the x445 and the EMC storage server are listed on Novell’s SuSE Supported Hardware website
  • D、Build a proof of concept system at the customer site to demonstrate functionality

正确答案:A

第10题:

An IBM Business Partner has sold a DS5020 and new IBM SAN switches to replace a customer EMC storage infrastructure. The customer dissatisfaction has arisen during the installation because according to the DS5020 interoperability matrix, two HP Proliant servers running Exchange have FC HBAs that are not supported. Which of the following is the most probable cause of the customer dissatisfaction()

  • A、The EMC storage specialist has not participated in the TDA meeting
  • B、The FC HBAs are 4 Gbps technology
  • C、The Technical and Delivery Assessment review actions were not executed
  • D、The customer should have checked that the HBAs are supported according to the HP storage interoperability matrix

正确答案:C