单选题An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be

题目
单选题
An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()
A

The administrator will need to perform an rg_move operation

B

The administrator will need to un-manage and re-manage the resource group

C

The administrator will need to execute the new start script from the command line

D

The new start script will be executed as part of the DARE operation to synchronize the cluster

如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A cluster administrator decides ti implement application monitoring in order to monitor both a web application and its supporting database. The plan is to use a single resource group prod_rg and to configure one monitor method for the web app and one monitor method for the database.  Which of the following statements best describes the need for custom resource monitor?()  

  • A、 Multiple application servers must be in a single resource group.
  • B、 Multiple application servers per resource group may be monitored.
  • C、 Multiple resource groups must each contain a single application server.
  • D、 Multiple application servers in a cluster cannot use process monitoring.

正确答案:B

第2题:

Company.com has a six-node concurrent resource group with an application that is accessed by  a web connection to the cluster nodes. How is the workload moved to another cluster node during a node failure?()  

  • A、 The concurrent application must control the web interface through application monitoring.
  • B、 A second resource group will be required to move the web application and IP label to a new node during a node failure.
  • C、 The concurrent resource group can support multiple IP labels through IP aliasing so all IP labels are defined in the concurrent resource group.
  • D、 The dynamic node priority facility in HACMP will relocate the web application and the IP label,if it is correctly defined in the application start and stop script.

正确答案:B

第3题:

A client has a temporary deployment of a new static application that needs to run for a short period of time and is not going to change.How can this deployment be achieved with a minimum of effort and time?()

A.Run a system WPAR and deploy the application.

B.Create a new LPAR and deploy the application.

C.Create an application WPAR to deploy the application.

D.Create an LPAR hosted by a VIO server and deploy the application.


参考答案:C

第4题:

To enhance the availability of an application running under HACMP, a decision was made to use  The application monitoring facility. The application consists of several components and can take several minutes to initialize. The components use socket communication and can be initialized in any order as long as it is a serial order. The customer’s concern is that if the application stop and start scripts are used during application monitoring recovery,it may take an extraordinary length of time to reset all of the application components.  What can be done to ensure the best recover time?()   

  • A、 Use a process monitor that restarts the named processes in the original start order.
  • B、 Use the defined application start and stop scripts to control the application if there is a failure.
  • C、 Use multiple application monitors for this resource group to enable the monitoring of the specific components of the resource group.
  • D、 Use application cleanup and restart scripts designed to determine the state of the various components of the application and start only the parts required.

正确答案:D

第5题:

An administrator has integrated a new application into an existing resource group. An application server withstart and stop scripts was defined and added to the resource group definition. The cluster was thensynchronized. How can the new application be started with minimal downtime?()

  • A、The administrator will need to perform an rg_move operation
  • B、The administrator will need to un-manage and re-manage the resource group
  • C、The administrator will need to execute the new start script from the command line
  • D、The new start script will be executed as part of the DARE operation to synchronize the cluster

正确答案:C

第6题:

An administrator is configuring an application monitor. Upon encountering an unrecoverable error the administrator does not want the resource group to failover. How can the application monitor be configured toachieve this?()

  • A、Configure the application monitor with a restart count of 0
  • B、Configure the application monitor with a monitor mode of Notify
  • C、Configure the application monitor with a notify method of Monitor
  • D、Configure the application monitor with a failure action of Notify

正确答案:D

第7题:

An administrator uses C-SPOC to change the user password for all nodes that belong to a  Resource group. The administrator must perform this operation on a node that is:()  

  • A、 included in the resource group.
  • B、 currently managing the resource group.
  • C、 not part of an application resource group.
  • D、 included in a cluster_admin resource group.

正确答案:A

第8题:

During a planning meeting, Company.com indicates that they intend to make a relational  Database highly available. The application has a pre-requisite that a kernel extension be loaded from /etc/inittab.  How would this be managed in an HACMP environment?()  

  • A、 It can be started with a crontab entry.
  • B、 It can be created as an Application Server.
  • C、 It can be added to a resource group as a dependency.
  • D、 It cannot be done because HACMP provides no method to order application start/stop scripts.

正确答案:B

第9题:

During initial cluster planning session, a requirement is mandated that application monitoring will  Be used to monitor the production database and three application servers. Since all the application servers rely on the database being active, only one resource group has been planned to manage the starting/stopping of the cluster resources.  How ill the initial design impact the use of application monitoring?()  

  • A、 Only one application server per resource group can be monitored.
  • B、 Process monitoring is part of RSCT and requires no special scripts.
  • C、 Any application can be monitored as long as it has an application server.
  • D、 Having all application servers in one resource group improves recovery time.

正确答案:A

第10题:

A cluster administrator has decided to add a cluster verification to the weekly maintenance scripts  That are run from corn.  When a cluster verification is performed,which of the following will require a custom verification method?()  

  • A、 HACMP ODM object classes
  • B、 HACMP Error Notification
  • C、 HACMP Topology & Resources
  • D、 HACMP Application Server Start/Stop scripts

正确答案:B