The resource group DNP has been configured.
The resource group option CWOF has been enabled.
The resource group option Inactive Takeover is set.
A resource group fallback timer has been configured.
第1题:
The IP subsystem fallover behavior of a two-node cluster is being testing in a large client organization. One of the tests is to simulate a network_down event and verify that HACMP movesthe single resource group to the standby node. What is the best way to simulate a network down condition?()
第2题:
An administrator has a 2 node cluster running PowerHA version 5.5. They remove a resource group from theactive cluster configuration. When performing a verify and synchronize of the cluster, the administrator getsthe following error: "migcheck[471]: cl_connect() error, nodename=Node1, rc=-1 cldare: A communication error prevents obtaining the VRMF from remote nodes. A DARE event cannot be run until this is corrected. Please ensureclcomd is running." What is the most likely cause of this error?()
第3题:
The en0 interface on Node1 of a two-node cluster has failed. This adapter is configured with a boot addressand under stable operations also has the service address of the cluster’s single resource group. The resourcegroup is configured with the fallback option. The HA network was configured for IPAT via aliasing and now theservice address is on the en1 interface in the cluster. The en0 interface has already been physically replacedand configured with the boot address. Which of the following will return the cluster to its original state andminimize cluster downtime?()
第4题:
An administrator has made several topology and resource group changes on one node in a running cluster.During verification and synchronization, using the "Emulate" option, many errors are reported. Theadministrator decided the best course of action was to roll back the changes. Prior to the changes beingmade, a cluster snapshot was taken. Which of the following actions will roll back the changes with the least disruption?()
第5题:
An administrator will be performing a PowerHA upgrade on a cluster from version 5.3 to version 5.5. Which ofthe following tasks will verify a successful migration?()
第6题:
A cluster administrator is performing fallover testing during a scheduled system outage. Node ’A’ Was forced down and eventually rebooted. When Node ’A’ reintegrates into the cluster, the resource group state is offline. No errors are found in reviewing the hacmp.out file. What could have been done to ensure the resource group was acquired when cluster processing was restarted on Node ’A’?()
第7题:
A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’. What type of configuration would cause this type of behavior?()
第8题:
During a cluster functionality test, and administrator performs a graceful stop for Node ’B’ in a three-node cluster. What is the expected state of the cluster after Node ’B’successfully completes?()
第9题:
A step in the HACMP test plan is to gracefully stop the cluster on a node and to verify that the Shared resources fallover to the standby node. To prepare for this testing step, both nodes in the two-node cluster are in a stable state with the single resource group active on Node ’A’. Which of the following is the best way to execute this portion of the test plan?()
第10题:
A two-node cluster provides NFS exports to a variety of UNIX clients. During fallover testing,it is determined that some clients are unable to mount the exported filesystems after fallover,and before node reintegration. It is verified that the filesystems belong to a resource group and are correct in /usr/es/sbin/cluster/etc/exports. Which of the following may provide a possible solution to this problem?()