第1题:
In which of the following cost estimating techniques are statistics models used:
A . nonparametric cost estimating
B . parametric cost estimating
C . life cycle cost estimating
D . bottom-up estimating
E . All of the above.
第2题:
The review for the specification completeness is performed during which of the following cycles.
A Award cycles
B requirements cycle
C requisition cycle
D solicitation cycle
E contractual cycle
第3题:
Which of the following are included in the Acquisition phase(s) of the project life cycle.
A . concept and development
B . development and planning
C . execution and phase-out
D . planning and implementation
E . concept and planning
第4题:
82 Which of the following are included in the Acquisition phase(s) of the project life cycle.
A. concept and development
B. development and planning
C. execution and phase-out
D. planning and implementation
E. concept and planning
第5题:
84 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above.
第6题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第7题:
141 Feasibility studies occur in which life cycle phase (s)?
A. Conceptual
B. Conceptual or Development
C. Execution
D. Preliminary planning
E. any life cycle phase
第8题:
Feasibility studies occur in which life cycle phase (s)?
A.Conceptual
B.Conceptual or Development
C.Execution
D.Preliminary planning
E.any life cycle phase
第9题:
166 In which of the following cost estimating techniques are statistics models used:
A. nonparametric cost estimating
B. parametric cost estimating
C. life cycle cost estimating
D. bottom-up estimating
E. All of the above
第10题:
● Feasibility studies occur in which life cycle phase (s)?
A Conceptual
B Conceptual or Development
C Execution
D Preliminary planning
E any life cycle phase