单选题The passage is primarily concerned with which of the following?A Describing the life cycle of the Plasmodium protozoan as it relates to the disease malariaB Comparing and contrasting the life cycles of the six variants of the Plasmodium protozoan known

题目
单选题
The passage is primarily concerned with which of the following?
A

Describing the life cycle of the Plasmodium protozoan as it relates to the disease malaria

B

Comparing and contrasting the life cycles of the six variants of the Plasmodium protozoan known to cause malaria

C

Addressing the public health implications of the life cycle of the Plasmodium parasite

D

Providing information on how a person can avoid infection with malaria

E

Describing the life cycle of the Anopheles mosquito as it relates to the transmission of the Plasmodium protozoan to humans

参考答案和解析
正确答案: D
解析:
主旨题。文章主要在介绍与疟疾原生动物疟原虫的生命周期,故应选A项。
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。
相似问题和答案

第1题:

In which of the following cost estimating techniques are statistics models used:

A . nonparametric cost estimating

B . parametric cost estimating

C . life cycle cost estimating

D . bottom-up estimating

E . All of the above.


正确答案:B

第2题:

The review for the specification completeness is performed during which of the following cycles.

A Award cycles

B requirements cycle

C requisition cycle

D solicitation cycle

E contractual cycle


正确答案:C

第3题:

Which of the following are included in the Acquisition phase(s) of the project life cycle.

A . concept and development

B . development and planning

C . execution and phase-out

D . planning and implementation

E . concept and planning


正确答案:C

第4题:

82 Which of the following are included in the Acquisition phase(s) of the project life cycle.

A. concept and development

B. development and planning

C. execution and phase-out

D. planning and implementation

E. concept and planning


正确答案:C

第5题:

84 In which of the following cost estimating techniques are statistics models used:

A. nonparametric cost estimating

B. parametric cost estimating

C. life cycle cost estimating

D. bottom-up estimating

E. All of the above.


正确答案:B

第6题:

During which phase of the project life cycle is the amount at stake lowest?

A concept

B development

C execution

D conclusion

E C and D


正确答案:A

第7题:

141 Feasibility studies occur in which life cycle phase (s)?

A. Conceptual

B. Conceptual or Development

C. Execution

D. Preliminary planning

E. any life cycle phase


正确答案:A

第8题:

Feasibility studies occur in which life cycle phase (s)?

A.Conceptual

B.Conceptual or Development

C.Execution

D.Preliminary planning

E.any life cycle phase


正确答案:A
A

第9题:

166 In which of the following cost estimating techniques are statistics models used:

A. nonparametric cost estimating

B. parametric cost estimating

C. life cycle cost estimating

D. bottom-up estimating

E. All of the above


正确答案:B

第10题:

● Feasibility studies occur in which life cycle phase (s)?

A Conceptual

B Conceptual or Development

C Execution

D Preliminary planning

E any life cycle phase


正确答案:A