● In crashing a task, you would focus on:

A As many tasks as possible.

B Non critical tasks.

C Accelerating performance of tasks on critical path.

D Accelerate performance by minimizing cost.

E A and D.


正确答案:C

第2题:

No two leaves from the same tree are ________.

A identical

B original

C analytical

D critical


参考答案A

第3题:

In crashing a task, you would focus on:

A.As many tasks as possible.

B.Non critical tasks.

C.Accelerating performance of tasks on critical path.

D.Accelerate performance by minimizing cost.

E.A and D.


正确答案:C
C

第4题:

Which of the following tasks does the tool Incident Packaging Service (IPS) perform?()  

  • A、 Cleans up the ADR by deleting files not associated with an incident uploaded to Oracle Support.
  • B、 Identifies all files associated with a critical error and adds them to a zip file to be sent to Oracle Support.
  • C、 Automatically opens a Service Request with Oracle Support for each critical error and sends all relevant files.
  • D、 Displays a high-level view of critical errors on the database home page.

正确答案:B

第5题:

ThefollowingcommandisissuedonaCiscoRouter:Router(configuration)loggingconsolewarningsWhichalertswillbeseenontheconsole?()

A.Warningsonly

B.debugging,informational,notifications,warnings

C.warnings,errors,critical,alerts,emergencies

D.notifications,warnings,errors

E.warnings,errors,critical,alerts


参考答案:C

第6题:

In the following statements about graph operations,which one is NOT correct?

A.Finding critical path is an operation on directed graph

B.Finding critical path is an operation on undirected graph

C.Spanning tree of a graph may not be unique

D.Minimum spanning tree of a graph may not be unique


正确答案:B

第7题:

critical micelle concentration:


正确答案:critical mlcelle concentration:临界胶束浓度表面活性剂分子缔合形成胶束的最低浓度。
criticalmlcelleconcentration:临界胶束浓度,表面活性剂分子缔合形成胶束的最低浓度。

第8题:

Standard deviation of project completion is _____ .

A a relationship of the uncertainty of critical path activities.

B an indicator of project end date target confidence

C a function of critical path, leveling and project costs.

D A and B

E All of the above.


正确答案:D

第9题:

On a hydrocarbon flammability chart the line which extends from 0% to 21.8% oxygen,lying tangent to the flammability range,is called the ______.

A.minimum oxygen content line

B.critical displacement line

C.critical dilution line

D.upper threshold limit


正确答案:C

第10题:

缓发临界delayed critical


正确答案: 需要缓发中子参与作用才能达到的临界。

更多相关问题