Use ESD equipment.
Verify correct voltages are being supplied.
Use a system board tester to check for compatibility issues.
Install compatible PCI cards
第1题:
While installing a new PCI card the administrator touched the motherboard. While powering on the server, a series of beeps were emitted and the server did not POST.Which of the following could be done to prevent this problem?()
A. Use ESD equipment.
B. Verify correct voltages are being supplied.
C. Use a system board tester to check for compatibility issues.
D. Install compatible PCI cards
第2题:
A.Add the fibre channel card as hared?Add the fibre channel card as ?hared?
B.Add the fibre channel card as irtual?Add the fibre channel card as ?irtual?
C.Add the fibre channel card as esired?Add the fibre channel card as ?esired?
D.Add the fibre channel card as equired?Add the fibre channel card as ?equired?
第3题:
The network administrator has just finished installing a new 10/100/1000 switch, but receives reports from the server administrator that servers connected to the new switch seem to be experiencing slow LAN connections. The network administrator checks the port connecting the new switch to the core switch and sees the following information:Which of the following is the MOST likely cause of the slow connections?()
A. The servers have not had VLAN tagging enabled on their NICs.
B. Speed and duplex have not been set.
C. VLAN tagging was not set on the trunk.
D. The servers have been connected with CAT5 cable.
第4题:
When installing a new Plug and Play sound card, a technician should turn off and unplug the computer; remove the computer’s cover; locate the sound card slot, insert and secure the card in the slot and:()
第5题:
An administrator just installed a new RAID controller card into a server. The firmware is current for the controller card. When the server is powered up the administrator notices that the RAID controller card is not recognized during POST. Which of the following is the cause of the problem?()
第6题:
A. Log the administrator password used
B. Test the air temperature
C. Update the network diagram
D. Review the evacuation procedures
第7题:
A technician is trying to install a previous-generation expansion card into their new laptop.However, the card refuses to fit into the expansion slot. Which of the following is MOST likely the reason?()
第8题:
A. Before inserting the PCIe network card in the case
B. After inserting the new PCIe network card in the case
C. They will be automatically loaded after installation
D. Load them concurrently with the PCIe network card
第9题:
A technician is installing a parallel PCI card. Which of the following is the IEEE standard for parallel?()
第10题:
An administrator receives a contract for a server install at a new building. Which of the followingshould be completed after installing the server?()