Which may be employed to shorten a schedule without changing the scope of the task?
A.Fast tracking.
B.Crashing
C.Releasing resources earlier from tasks which were scheduled with a late start.
D.Alter to task priorities.
E.A or B
第2题:
85 Scheduling is the process by which decisions are made concerning:
A. Tasks to be accomplished.
B. Personnel/organization that will be assigned to accomplish the task.
C. Time when the tasks are to be completed.
D. All of the above.
E. A and C only.
第3题:
Which of the following can result in misinterpretation of the statement of work?
A.Using imprecise language (i.e. nearly, approximately)
B.Mixing tasks, specifications, special instructions and approvals
C.No pattern, structure or chronological order
D.Wide variation in the size of tasks or details of work
E.All of the above
第4题:
● The critical path is calculated by
A subtracting the end date of task one from the start date of task two.
B determining which tasks have the least amount of total slack.
C totaling the time for all activities.
D determining the shortest path through the network.
E Determining which tasks have the most slack
第5题:
177 Which may be employed to shorten a schedule without changing the scope of the task?
A. Fast tracking.
B. Crashing
C. Releasing resources earlier from tasks which were scheduled with a late start.
D. Alter to task priorities.
E. A or B
第6题:
Scheduling is the process by which decisions are made concerning:
A.Tasks to be accomplished.
B.Personnel/organization that will be assigned to accomplish the task.
C.Time when the tasks are to be completed.
D.All of the above.
E.A and C only.
第7题:
80 Which of the following can result in misinterpretation of the statement of work?
A. Using imprecise language (i.e. nearly, approximately)
B. Mixing tasks, specifications, special instructions and approvals
C. No pattern, structure or chronological order
D. Wide variation in the size of tasks or details of work
E. All of the above
第8题:
The critical path is calculated by
A.subtracting the end date of task one from the start date of task two.
B.determining which tasks have the least amount of total slack.
C.totaling the time for all activities.
D.determining the shortest path through the network.
E.Determining which tasks have the most slack
第9题:
● Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
第10题:
● Which may be employed to shorten a schedule without changing the scope of the task?
A Fast tracking.
B Crashing
C Releasing resources earlier from tasks which were scheduled with a late start.
D Alter to task priorities.
E A or B