PDCH分为哪两种状态的信道:()
第1题:
6 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A. Increase, increase.
B. Increase, decrease.
C. Decrease, decrease.
D. Decrease, increase.
E. Remain the same, return to customer
第2题:
A.conserve
B.deserve
C.preserve
D.reserve
第3题:
Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A . Increase, increase.
B . Increase, decrease.
C . Decrease, decrease.
D . Decrease, increase.
E . Remain the same, return to customer.
第4题:
交换机当前状态处于局部配置模式的是 (68) 。
A. switch>
B. switch
C. switch(config-if)
D. switch(config)
第5题:
A.algorithm=failover
B.algorithm=round_robin
C.reserve_policy=no_reserve
D.reserve_policy=single_path
第6题:
A、queued到pending_delete
B、active到queued
C、queued到active
D、queued到deleted
第7题:
第8题:
There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A . Management reserve, unplanned allowance fund.
B . Management reserve, contingency.
C . Contingency fund, management reserve.
D . Unplanned allowance fund, budgetary reserve.
E . Unplanned reserve, planned reserve.
第9题:
A.Switch(config)#interface port-channel1
B.Switch(config)#channel-group 1 mode active
C.Switch#interface port-channel 1
D.Switch(config-if)#channel-group 1 mode active
第10题: