The room temperature has reached 23C (73.4F).
A Blade within the chassis has been shut down.
The ambient temperature in the data center has increased
One of the additional System X servers in the BladeCenter rack has failed.
第1题:
A medical customer has a rack with four BladeCenter H chassis that have been operating normally for several months. After installing a new rack of servers in the data center, the system administrator notices the blowers in the BladeCenters have increased their speed. Which of the following caused this problem? ()
第2题:
An SNMP alert has been generated by a server in the main data center.The alert stated that the internal temperature of the server has exceeded the threshold.No other servers in the rack have experienced problems,and no other alerts have come from that server about any other events.Which of the following is the cause of this issue?()
第3题:
The network administrator has just finished installing a new 10/100/1000 switch, but receives reports from the server administrator that servers connected to the new switch seem to be experiencing slow LAN connections. The network administrator checks the port connecting the new switch to the core switch and sees the following information:Which of the following is the MOST likely cause of the slow connections?()
A. The servers have not had VLAN tagging enabled on their NICs.
B. Speed and duplex have not been set.
C. VLAN tagging was not set on the trunk.
D. The servers have been connected with CAT5 cable.
第4题:
You have a request to put together IBM System x and blade servers attached to IBM DS4000 Storage: all in a rack. Your customer is also requesting services. What IBM resource will help you put these different products together?()
第5题:
An IBM XIV system with nine modules and 2 TB disks is being proposed to a customer who needs to increase disk capacity in the data center. The customer is concerned about data growth andcost after the initial purchase. Which of the following factors of the solution should be stressed to the customer to address data growth?()
第6题:
After a server has been installed into a rack, an administrator must ensure which of the following?()
第7题:
A customer is interested in reducing energy consumption and infrastructure consolidation for space. The customer needs a maximum of 14 servers in 7U rack. Which IBM BladeCenter Chassis should be recommended? ()
第8题:
A customer has an existing high availability SAN environment with CLARiiON, which has been stable for 16 months. They have recently experienced several outages with their current storage systems. They need to purchase additional storage and have asked about tier 1 storage. They are concerned with connecting their existing storage and servers without trouble.Which resource should be consulted while developing the solution options?()
A. Disk Magic
B. TPC for Data
C. CLARiiON Procedure Generator
D. System Storage Interoperability Center
第9题:
A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers. This is the first p650 in the enterprise. What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
第10题:
A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers. Which of the following should the Sales Specialist emphasize to address the pricing difference?()