Test Ethernet fallover and bring all of the resource groups online.
Upgrade the firmware on all Ethernet adapters and bring all of the resource groups online.
Verify all necessary applications and resource groups are functioning properly and test ethernet fallover on all nodes.
Verify all necessary applications and resource groups are functioning properly and bring all of the resource groups online.
第1题:
Companycom wants to apply a PTF to the p5 590 system. After doing a preview install, the output shows there is insufficient space in the /usr filesystem. The root volume group has no available physical partitions left. They do not want to add additional disk drives to the system, but have a jfs2 filesystem that is only 8% used. What could they do to utilize space in the jfs2 filesystem to apply this PTF?()
第2题:
A graphics card has been added to the system. After rebooting, the system hangs during the login process with a blue screen indicating "CDE please wait". Which of the following procedures should be performed next?()
第3题:
A new HACMP maintenance level has recently been released. An administrator is creating a project plan that is required for applying the updates for a three-node production cluster. To minimize downtime,what is the best way to accomplish the updates on all cluster nodes?()
第4题:
A company just hired a new plant maintenance manager, and they are concerned about the number of corrupt asset records in the present system. In future they want to prevent this from happening. When implementing the new solution, what is recommended?()
第5题:
You are the network administrator for All network servers run Windows Server 2003. Recently, another network administrator create a scheduled task to perform a normal backup of Microsoft Exchange Server 2003 compuer every Saturday night. You need to perform maintenance tasks on the Exchange server on this Saturday night only. If the backup starts while you are performing the maintenance tasks,data might be corrupted. You need to ensure that the backup task does not start while you perform the maintenance tasks. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.()Choose two.)
第6题:
A recommended PTF is released to resolve reliability issues with bos .net.tcp.server. A Maintenance windows has been scheduled to install the PTF on all nodes. In order to complete the maintenance,what are the next logical steps to be completed after the install of the PTF on all nodes?()
第7题:
Which of the following should be performed after a maintenance kit has been applied and fullfunctionality tested?()
第8题:
When is the most appropriate time to conduct a Pre-install Solution Assurance Review?()
第9题:
After a client has developed a security policy, what is recommended that they do next?()
第10题:
A work order has been created to perform corrective maintenance on a defective generator. All required information has been provided in the work order, but required materials are not in stock and have to be ordered. What is the status of the work order, after a maintenance manager has approved the work order? ()